JOHN W. HICKENLOOPERMayor |
BID SUMMARY |
|||||||||
|
City and County of Denver Department of Public Works Contract Administration 201 West Colfax Dept. 611 Denver, CO 80202 |
DATE: Friday, June 20, 2008 TIME: 11:00 AM
CONTRACT NO.: CE80192 MAIN PROJECT FUNDING NUMBER: PI80708_107
PROJECT NAME: CHERRY CREEK DRIVE SOUTH CONSTRUCTION, UNIVERSITY TO STEELE - PHASE 1
PROJECT MANAGER: Dennis Ohlrogge PHONE: (720) 913-4546
|
|||||||||
|
Engineer’s Estimate: $2,041,319.10 |
||||||||||
|
Prequalification Required: CE-6 $2,500,000.00 |
||||||||||
|
Number of Addenda:3 |
BIDS
|
|||||||||
|
MWBE Goals: 12.00% |
|
|
|
|
|
|
|
|||
|
Bidders: |
New Design Construction Company |
Castle Rock Construction Company of Colorado, LLC |
Concrete Works of Co., Inc. |
Concrete Express, Inc. |
|
|
|
|
||
|
Bid Guarantee Submitted |
þ |
þ |
þ |
þ |
|
|
|
|
||
|
Addenda Acknowledged |
þ |
þ |
þ |
þ |
|
|
|
|
||
|
Bidder Disclosure Submitted |
þ |
þ |
þ |
þ |
|
|
|
|
||
|
Project Goal Submitted |
12.00% |
12.00% |
12.01% |
12.00% |
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
||
|
TOTAL BID AMOUNT:
|
$1,932,093.36 |
$2,089,849.65 |
$2,146,416.45 |
$2,563,000.00 |
|
|
|
|
||
|
Bid Rank: |
1 |
2 |
3 |
4 |
|
|
|
|
||