Central Denver Transportation Plan
 Related Links Minimize
 Print   
LOCATE IT!
Find city services near your home or business.
 Central Denver Transportation Plan Minimize
Washington/Clarkson Modifications Completed 
 
The next phase of street modifications resulting from the recommendations of the Central Denver Transportation Study (CDTS) was completed Sunday, December 7, 2003.

The solutions selected for this phase are to emphasize the neighborhood character of the streets by increasing the number of on street parking spaces.

Washington Street and Clarkson Street between 8th Ave and 14th Avenue will be modified to provide one lane of traffic with parking on both sides of the street.

Downing/Corona Streets Modified
Traffic Lane Conversion Will Allow More Parking

On Monday, December 16, 2002, the Public Works Department converted one traffic lane on Downing Street between 9th Avenue and 12th Avenue and one traffic lane on Corona Street between 14th Avenue and 10th Avenue to parking lanes.



Implementation of Street Modifications Continues
The next round of street traffic modifications resulting from the recommendations of the Central Denver Transportation Study (CDTS) were installed during the first week of August, 2000.

The solutions selected for this round of modifications are to emphasize the neighborhood character of the streets. Several one way streets will be modified to reduce the number of traffic lanes and to increase on street parking.  The modifications will be installed on the following streets:

  • Washington Street from 6th Avenue to Speer Blvd.--One lane of traffic with parking on both sides of the street
  • Clarkson/Emerson Streets from Speer Blvd to 8th Ave--One lane of traffic with parking on both sides of the street
  • Corona Street from 8th Ave to Speer Blvd-- One lane of traffic with parking on both sides of the street
  • Downing Street from Speer Blvd to 8th Ave--One lane of traffic with parking on both sides of the street

    Following these modifications traffic studies including traffic counts, speed studies, traffic accident conditions, and intersection operations analysis will be conducted to determine what changes in traffic characteristics have occurred following these modifications.



    Phase 1 Implementation of Street Modifications to Date
    • Washington and Emerson between I-25 and Speer Blvd. converted to one lane operation with full-time parking on both sides of the street
    • 8th Avenue - between Colorado Blvd. and Columbine converted to two lane one-way operation with full time parking on both sides of the street