Iowa Avenue Extension Storm Sewer Project

The Iowa Avenue Extension is being managed by Denver Public Works. The work includes installing a new storm sewer system which starts just east of Broadway on Iowa Avenue and runs east four blocks to Logan Street.  Once in Logan Street it proceeds south four blocks to Asbury Avenue.

When complete the project will add approximately 4,000 feet of 54-inch / 60-inch diameter pipe and multiple catch basins to help capture and convey stormwater.  

In order to accomplish this work, sections of Iowa Avenue and then Logan Street will require closures to safely and effectively install the storm sewer system.  Closures will also be required on residential streets however local access will be maintained. 

The new storm sewer, which costs approximately $2.5 million, will begin in the spring of 2013 with completion in the winter of 2013.


Project Information

Project Schedule

  • Utility Relocations (Fall 2012 to Spring 2013)
  • Storm Sewer Construction (Spring 2013 to Winter 2013)

Project Contacts

BT Construction
Kevin Juliano 303.469.0199        
Herb Jones 303.591.3446     
Denver Public Works
Jason Wennen 303.446.3628         
Bill Rider 720.295.5066       