November 2009 - Pre-assessment public meetings
December 2009 - April 2010 - Environmental Site Assessment Phase I
March 2010 - Asbestos survey
May 2010 - Environmental Site Assessment Phase II
July 2010 - Public meetings regarding findings
October 2010 - Groundbreaking for first phase of construction