Denver Justice Center
LOCATE IT!
Find city services near your home or business.
 
 Project Status Minimize

                                                                                                       Last Updated on November 10, 2009

COURTHOUSE

            MILESTONES:

·         Demolition Start: June 2007

·         Construction Start: August 2007

·         Projected Occupancy: August 2010 

            STATUS:  Project 78% Complete

·         Exterior Stonework – 99%

·         Curtain Wall – 99%

·         Interior Framing/Drywall/Painting – 95%

·         HVAC – 85%

·         Electrical – 75%

·         Courtroom Millwork:  Level 2  & Level 3 – 85%

·         Courtroom Millwork:  Level 4  & Level 5 – 50%

·         Terrazzo:  80%

·         Interior Stone: 95%

·         Site work – 30%

·         Plaza landscape walls with granite veneer – 50%

·         Atrium and stair – 75% 

DETENTION CENTER

            MILESTONES:

·         Demolition Start: November 2006

·         Construction Start: March 2007

·         Projected Occupancy: April 2010 

STATUS:  Project 90% Complete

·         Exterior Stone and Site work in progress – 99%

·         Framing/Drywall: In progress Levels 1-5 – 92%

·         Mechanical/Electrical/Plumbing:  Throughout – 90%

·         Painting:  In progress Levels 1-5 – 90%

·         Glazing:  In progress levels 2-5  - 95%

·         Terrazzo: In progress Levels 1-2 – 98%

·         Roofing: 98%

POST OFFICE/PARKING GARAGE

·         Completed June 2007

·         Contractor:  Haselden Construction Co.

·         Architect /Engineer:  AR7 Architects

·         Occupants:

o        1st Floor: US Post Office

o        Hensel Phelps Jobsite Office

o        Levels 2-5:  Parking Structure 

SMITH ROAD KITCHEN

·         Project Complete and Operating on May 2009 

SMITH ROAD NEW HOUSING UNIT

MILESTONES:

·         Design Services Agreement Completed

·         Master planning review and approved

·         Schematic Design Phase: 100%

·         Design Development Phase: 100%

·         Construction Documents Phase: 10%

·         Construction Start: June 2010

·         Construction Complete: June 2012