Last Updated on November 10, 2009
COURTHOUSE
MILESTONES:
· Demolition Start: June 2007
· Construction Start: August 2007
· Projected Occupancy: August 2010
STATUS: Project 78% Complete
· Exterior Stonework – 99%
· Curtain Wall – 99%
· Interior Framing/Drywall/Painting – 95%
· HVAC – 85%
· Electrical – 75%
· Courtroom Millwork: Level 2 & Level 3 – 85%
· Courtroom Millwork: Level 4 & Level 5 – 50%
· Terrazzo: 80%
· Interior Stone: 95%
· Site work – 30%
· Plaza landscape walls with granite veneer – 50%
· Atrium and stair – 75%
DETENTION CENTER
MILESTONES:
· Demolition Start: November 2006
· Construction Start: March 2007
· Projected Occupancy: April 2010
STATUS: Project 90% Complete
· Exterior Stone and Site work in progress – 99%
· Framing/Drywall: In progress Levels 1-5 – 92%
· Mechanical/Electrical/Plumbing: Throughout – 90%
· Painting: In progress Levels 1-5 – 90%
· Glazing: In progress levels 2-5 - 95%
· Terrazzo: In progress Levels 1-2 – 98%
· Roofing: 98%
POST OFFICE/PARKING GARAGE
· Completed June 2007
· Contractor: Haselden Construction Co.
· Architect /Engineer: AR7 Architects
· Occupants:
o 1st Floor: US Post Office
o Hensel Phelps Jobsite Office
o Levels 2-5: Parking Structure
SMITH ROAD KITCHEN
· Project Complete and Operating on May 2009
SMITH ROAD NEW HOUSING UNIT
MILESTONES:
· Design Services Agreement Completed
· Master planning review and approved
· Schematic Design Phase: 100%
· Design Development Phase: 100%
· Construction Documents Phase: 10%
· Construction Start: June 2010
· Construction Complete: June 2012