Last Updated on January 4, 2010
COURTHOUSE
MILESTONES:
· Demolition Start: June 2007
· Construction Start: August 2007
· Projected Occupancy: July 2010
STATUS: Project 83% Complete
· Exterior Stonework – 99%
· Curtain Wall – 99%
· Interior Framing/Drywall/Painting – 97%
· HVAC – 94%
· Electrical – 85%
· Courtroom Millwork: Level 2 & Level 3 – 85%
· Courtroom Millwork: Level 4 & Level 5 – 50%
· Terrazzo: 90%
· Interior Stone: 99%
· Site work – 40%
· Plaza landscape walls with granite veneer – 55%
· Atrium and stair – 80%
DETENTION CENTER
MILESTONES:
· Demolition Start: November 2006
· Construction Start: March 2007
· Projected Occupancy: April 2010
STATUS: Project 90% Complete
· Exterior Stone and Site work in progress – 99%
· Framing/Drywall: In progress Levels 1-5 – 100%
· Mechanical/Electrical/Plumbing: Throughout – 95%
· Painting: In progress Levels 1-5 – 95%
· Glazing: In progress levels 2-5 - 95%
· Terrazzo: In progress Levels 1-2 – 100%
· Roofing: 98%
POST OFFICE/PARKING GARAGE
· Completed June 2007
· Contractor: Haselden Construction Co.
· Architect /Engineer: AR7 Architects
· Occupants:
o 1st Floor: US Post Office
o Hensel Phelps Jobsite Office
o Levels 2-5: Parking Structure
SMITH ROAD KITCHEN
· Project Complete and Operating on May 2009
SMITH ROAD NEW HOUSING UNIT
MILESTONES:
· Design Services Agreement Completed
· Master planning review and approved
· Schematic Design Phase: 100%
· Design Development Phase: 100%
· 50% Construction Documents – 100%
· 80% Construction Documents – 80%
· Bid Documents: 0%
· Construction Start: June 2010
· Construction Complete: June 2012