Project Status

 

COURTHOUSE

            MILESTONES:

·         Demolition Start: June 2007

·         Construction Start: August 2007

·         Construction Completion: May 2010

·         Projected Occupancy: July 2010

 

            STATUS:  Project 100% Complete

·         Exterior Stonework – 100%

·         Curtain Wall – 100%

·         Interior Framing/Drywall/Painting – 100%

·         HVAC – 100%

·         Electrical – 100%

·         Courtroom Millwork:  Levels 2  3 4 5 – 100%

·         Terrazzo:  100%

·         Interior Stone: 100%

·         Site work – 100%

·         Plaza landscape walls with granite veneer – 100%

·         Atrium and stair – 100%

 

DETENTION CENTER

            MILESTONES:

·         Demolition Start: November 2006

·         Construction Start: March 2007

·         Substantial Completion (TCO): March 8, 2010

·         Projected Occupancy: May 2010

 

STATUS:  Project 100% Complete

·         Site work in progress – 100%

·         Mechanical/Electrical/Plumbing:  Throughout – 100%

·         Painting:  In progress Levels 1-5 – 100%

·         Glazing:  In progress levels 2-5  - 100%

·         Project Closeout and completion of final Certificate of Occupancy complete.

 

POST OFFICE/PARKING GARAGE

·         Completed June 2007

·         Contractor:  Haselden Construction Co.

·         Architect /Engineer:  AR7 Architects

·         Occupants:

o        1st Floor: US Post Office

o        Hensel Phelps Jobsite Office

o        Levels 2-5:  Parking Structure

 

SMITH ROAD KITCHEN

·         Project Complete and Operating on May 2009

 

SMITH ROAD NEW HOUSING UNIT

MILESTONES:

·         Design Services Agreement Completed

·         Master planning review and approved

·         Schematic Design Phase: 100%

·         Design Development Phase: 100%

·         50% Construction Documents – 100%

·         95% Construction Documents – 100%

·         Bid Documents – 100%

·         Bid Due Date: April 23, 2010 – 11:00 a.m.

·         Construction Start: June 2010

·         Construction Complete: June 2012

Feedback