Contract 202263315 Connecting Auraria

Closed July 14, 2022, 11:00 AM

  • Reference numberContract 202263315
  • StatusAwarded
  • SummaryThis project is the construction phase to remove and replace the Larimer Street bridge over Cherry Creek and Cherry Creek Trail and traffic signal upgrades at the intersections of Larimer Street and NB and SB Speer Blvd. Work will include demo of the existing bridge, earthwork, construction of a new bridge.
  • Winning entity
    Hamon Infrastructure, Inc.
  • Value$6,345,997.02
  • Date awardedOctober 13, 2022

General Statement of Work

This project is the construction phase to remove and replace the Larimer Street bridge over Cherry Creek and Cherry Creek Trail and traffic signal upgrades at the intersections of Larimer Street and NB and SB Speer Blvd. Work will include demo of the existing bridge, earthwork, construction of a new bridge.  In addition, the signal upgrades at the two intersections includes demo of the existing signal equipment, demo of the existing curb ramps, installation of upgraded signal equipment, construction of new curb ramps, and associated streetscape elements and landscaping. Traffic control and erosion control will be ongoing components of the project.

Elevate Denver is a 10-year, $937 million general obligation bond program approved by voters in 2017, that will enhance the City and County of Denver by providing critical improvements to the City’s infrastructure – improving our roads, sidewalks, parks, recreation centers, libraries, cultural centers, public-owned buildings and safety facilities. More information can be found at www.denvergov.org/elevatedenver.

Statement of Quantities(PDF, 186KB) (Updated)

Estimated Construction Cost: Between $5,200,000.00 and $5,700,000.00

Virtual Pre-Bid Meeting on June 14, 2022 at 11:00 a.m.

To access the meeting, please call (720) 388-6219 and enter conference ID: ­­­­952 318 485#.

Pre-Bid Meeting Agenda(PDF, 332KB)

Sign-in Sheet(PDF, 149KB)

Questions Deadline: June 21, 2022 at 10:00 a.m. local time

Bid Opening on July 14, 2022 at 11:00 a.m.

Bids will be received and accepted via the online electronic bid service, www.QuestCDN.com and will be read aloud. To access the bid opening teleconference, please call (720) 388-6219 and enter conference ID: ­­­­234 027 238#. To submit responses, click the online bidding button at the top of advertisement. Contractors must be on the plan holders list through QuestCDN for proposals to be accepted. Contractors will be charged a fee of $30.00 to submit a proposal electronically.

Plans Available June 6, 2022

Digital Download

QuestCDN Project # 8216697

Plan Cost: $15.00

MWBE Goal: 19%

Prequalification: 1G(1) Major Bridge Work at or above the $6,000,000.00 monetary level

Contract Administrator: Regina Diaz - doti.procurement@denvergov.org

Miscellaneous

Contracts for construction, reconstruction, and remodeling are subject to the City prevailing wage rate requirements established pursuant to Section 20-76, D.R.M.C.

City contracts are subject to payment of City Minimum Wage established pursuant to Section 20-82 through 20-84 D.R.M.C.

As the City’s best interests may appear, the Executive Director of the Department of Transportation and Infrastructure reserves the right to waive informalities in, and to reject any or all, submittals.

Publication Dates:           June 6, 7, 8, 2022

Published In:                   The Daily Journal