National Western Livestock Center Design

Photo shows two construction workers at the National Western Center.

Why we did this audit

Community members raised concerns about the National Western Center project’s effects on Denver businesses. This audit was prioritized based on these concerns and our ongoing commitment to assess projects impacting the local economy.

Key facts

  • The National Western Center project is renovating the National Western Complex.

  • The historic National Western Stock Show has been hosted at this location since before the construction of the complex in the 1980s, which officially began in 1906.

  • The Mayor’s Office of the National Western Center was created to oversee the City and County of Denver’s role in the National Western Center project. One such role is the design of the new Livestock Center.

  • The Livestock Center, expected to be completed by the end of 2025, will host the National Western Livestock Show  going forward.

Why this matters

Renovating the campus that hosts the National Western Stock Show is important to the culture and economy of Denver. The Mayor’s Office of the National Western Center plays a key role in ensuring the city’s investment in this project creates value and serves the entire community.

Finding

FINDING – The design phase had inadequate governance, documentation, and project delivery oversight

  • The Mayor's Office of the National Western Center did not use a clear, documented process to choose the "construction manager/general contractor" project delivery method. It also did not confirm whether this method was the best option for the Livestock Center project.

  • The office did not make sure subconsultants were properly reviewed or competitively selected.

  • The office did not use an independent cost estimator to ensure the city paid a fair, reasonable price for design work.

  • The office did not maintain all required financial records in the city's system of record. It also did not properly manage invoice processing, causing late payments to subconsultants.

  • The office did not properly manage who could access project data, which made it more likely that the data could be accessed without authorization.

Recommendations

1.1 Develop and document project-level delivery method evaluation – The Mayor’s Office of the National Western Center should establish and follow a formal process to compare delivery methods for each construction project. This should include:

  • Using structured evaluation criteria.
  • Documenting risk assessments.
  • Clearly recording the decisions made that show why construction manager/general contractor is the best choice when used.

The process should align with the city’s construction manager/general contractor guidance to ensure transparency, consistency, and that each project uses the most appropriate delivery method.

The Mayor’s Office of the National Western Center should also update its procurement plan to require project-specific documentation and retain these records to support transparency and public accountability.

Mayor’s Office of the National Western Center – Disgree 

1.2 Develop, document, and implement formal construction manager/general contractor project management policies – The Mayor’s Office of the National Western Center should develop or adopt, document, and implement a comprehensive set of policies and procedures to manage construction manager/general contractor projects from start to finish.

These policies should cover key areas such as project delivery selection, preconstruction and construction oversight, risk management, change order processing, and postconstruction activities. The policies should align with the city’s 2023 construction manager/general contractor guidance and all future updates to reflect leading practices.

Mayor’s Office of the National Western Center – Disagree

1.3 Develop and implement policies and procedures for managing design consultant contracts – The Mayor’s Office of the National Western Center should develop and implement policies and procedures for managing design consultant contracts that include:

  • Using mandatory independent cost estimations before negotiating fees or approving additional service requests or change orders.
  • Implementing a conflict-of-interest review process when the primary consultant proposes performing additional work.
  • Formally evaluating additional service requests or change orders to ensure alternatives are considered and costs are reasonable.
  • Clearly documenting standards for decision making, issue resolution, and project oversight.

Mayor’s Office of the National Western Center – Disgree

1.4 Documentation and transparency for design selection should be strengthened – The Mayor’s Office of the National Western Center should develop and follow clear procedures to fully document its design selection process, including how “Selection Committee” members are chosen and kept confidential, how proposals and interviews are scored, and how contract prices are negotiated.

The Mayor’s Office of the National Western Center should also ensure all related records are kept for at least seven years, in line with the city’s retention policy and industry leading practices for transparent construction manager/general contractor delivery.

Mayor’s Office of the National Western Center – Disagree

1.5 Develop and enforce formal procedures for subconsultant selection and approval – The Mayor’s Office of the National Western Center should develop and implement formal procedures to review, evaluate, and approve all subconsultants proposed for design projects before work begins. This should include:

  • Ensure all subconsultants selections comply with fair and competitive procurement standards. Require design consultants to submit all executed subcontracts for city review before work begins.
  • Review subcontract terms to ensure they do not conflict with the terms of the prime contract and meet city requirements.
  • Maintain all subcontract records in line with city’s retention policies.

The Mayor’s Office of the National Western Center should also require primary consultants to submit subcontracts for review and maintain these records in line with city retention requirements.

Mayor’s Office of the National Western Center – Disagree

1.6 Hire an independent cost estimator for all future construction manager/general contractor projects – The Mayor’s Office of the National Western Center should adopt the Department of Transportation & Infrastructure’s construction manager/general contractor 2023 guidance and hire independent cost estimators for all future construction manager/general contractor projects. This should include:

  • Using independent cost estimation to provide a reasonableness and fairness check on proposals for work.
  • Using independent cost estimation to provide an unbiased assessment of costs to help ensure the city pays a fair price.
  • Using independent cost estimation to provide the city with more information before negotiating contracts for its projects.

Mayor’s Office of the National Western Center – Disagree

1.7 The Mayor’s Office of the National Western Center must follow the city’s fiscal rules – The Mayor’s Office of the National Western Center leaders should implement a control process to ensure all invoice packet documentation is uploaded into Workday upon submission to the Department of Transportation & Infrastructure. This should include a formal checklist and verification step before being submitted.

Also, staff responsible for invoice processing should receive training on the requirements National Western Center should also clarify and document roles and responsibilities across all project partners to ensure documentation storage expectations are consistently followed.

Mayor's Office of the National Western Center – Agree, Implementation Date – Dec. 19, 2025

1.8 Enforce timely processing of primary and subconsultant invoices – The Mayor’s Office of the National Western Center should strengthen oversight of primary consultant invoice processing to ensure timely payments to subconsultants. Specifically, it should:

  • Require Populous (and any other primary consultant) to submit complete, accurate, and timely invoices, and enforce this through clear contractual requirements and regular monitoring.
  • Develop written procedures to track subconsultant invoice aging and escalate delays when invoices are not submitted on time.
  • Use existing project management authority under Executive Order No. 8 to hold primary consultants accountable for meeting prompt payment standards.
  • Work with the Department of Finance and City Attorney’s Office to clarify enforcement options for when repeated delays occur.

Mayor's Office of the National Western Center – Disagree

1.9 Develop internal governance documents to support Procore system management – The Mayor’s Office of the National Western Center should identify an appropriate systems governance framework, such as the Center for Internet Security’s “18 CIS Critical Security Controls” framework or ISACA’s “Control Objectives for Information Technology” framework and use it to guide the development of internal governance documents for using Procore. Examples of appropriate governance documentation include:

  • Formal policies for how the system will be administered, including identifying appropriate business owners of system data to review administration activities.
  • Formal procedures to guide provisioning, deprovisioning, and reviewing user accounts.
  • Documenting these activities as they occur with management review and approval of actions taken.
  • Documenting formal retention approval by managers for when dormant accounts are kept active.

All evidence of these processes should be maintained in accordance with the city’s retention policies.

Mayor's Office of the National Western Center – Agree, Implementation Date – Dec. 19, 2025

Auditor's addendums

Auditor’s addendum to agency response for Recommendation 1.1

The Mayor’s Office of the National Western Center says it evaluated delivery methods in its 37-page “Procurement Plan.” However, as noted in the audit, this plan was applied programwide and did not include a formal, documented, project-level evaluation for the Livestock Center.

The plan did not contain structured evaluation criteria, a project-specific risk assessment, or a documented comparison showing why the construction manager/general contractor method was the best fit for this project.

This approach does not align with leading practices outlined in the state of Colorado’s “Construction Manager/General Contractor Manual” or the city’s guidance, both of which call for project-level evaluations and documentation of delivery method decisions.

Saying that the method was “most advantageous” is not a substitute for a transparent, criteriabased process. Without project-specific documentation, the Mayor’s Office of the National Western Center cannot demonstrate that its decision was objective, risk-informed, or in the city’s best interest.

We reaffirm our finding and recommendation.

Auditor’s addendum to agency response for Recommendation 1.2

The Mayor’s Office of the National Western Center says that its management of construction manager/general contractor projects aligns with industry best practices and that it provided all requested documentation. However, the audit found the office lacked formal, written policies and procedures for managing construction manager/general contractor projects and design consultant contracts during the Livestock Center project.

Instead, staff relied on informal workflows and process flowcharts that did not provide sufficient guidance for managing complex capital projects. The audit identified no documented procedures for critical areas such as delivery method management, risk oversight, or day-to-day supervision of Populous and its subconsultants. Office leaders could not provide consistent records of meetings or management activities, and meeting minutes revealed gaps and extended periods without documented engagement.

The 2018 “Procurement Plan” cited by office leaders primarily focused on procurement and preconstruction services and did not serve as a comprehensive project management guide. This absence of formal policies is inconsistent with leading practices outlined in the city’s 2023 construction manager/general contractor guidance, the state of Colorado’s “Construction Manager/General Contractor Manual,” and the Government Accountability Office’s “Standards for Internal Control in the Federal Government.” These sources emphasize the necessity of clear, documented procedures to ensure accountability, consistency, and effective oversight.

Also, the office relied heavily on cost data submitted by Populous, including payment certifications that consistently underreported costs by over $68,000 for multiple years. These errors went undetected until 2025 without explanation. Despite this, the office continued to rely on Populous’ documentation without independent verification or procedures to prevent such issues.

The Mayor’s Office of the National Western Center’s dependence on informal tools and professional judgment falls short of industry standards and increases the risk of mismanagement, cost overruns, and diminished public accountability.

We reaffirm our finding and recommendations 1.2 and 1.3.

Auditor’s addendum to agency response for Recommendation 1.3

See the auditor’s addendum included with Recommendation 1.2.

Auditor’s addendum to agency response for Recommendation 1.4

The Mayor’s Office of the National Western Center says it followed the Department of Transportation & Infrastructure’s “Defined Steps” process and complied with city record retention policies. However, the audit found no evidence supporting this claim.

The office did not retain key records including Selection Committee members’ scores, evaluation notes, and contract negotiation documents, despite the city’s policy requiring purchasing records be kept for seven years. Without these documents, the fairness and competitiveness of selecting Populous cannot be verified.

Committee member selection lacked documentation on how members were chosen, their qualifications, or how confidentiality was maintained. Instead, office leaders relied on undocumented verbal discussions, reducing transparency and accountability.

Leading industry guidance from the National Academies of Science, Engineering, and Medicine emphasizes that design selection must be transparent to build trust and ensure successful construction manager/general contractor delivery. The absence of documentation violates these principles as well as city policies.

The Mayor’s Office of the National Western Center’s response does not address these significant gaps in documentation and transparency. Therefore, the recommendation to strengthen documentation and transparency remains necessary to protect public trust and ensure fair competition.

We reaffirm our finding and recommendation.

Auditor’s addendum to agency response for Recommendation 1.5

The Mayor’s Office of the National Western Center says it formally evaluated the proposed subconsultants as part of the prime consultant’s team and that the prime consultant is responsible for retaining all records. However, the audit found no evidence that the office independently reviewed or approved any subconsultants or their contracts during the Livestock Center design project.

The office did not obtain or retain copies of subcontracts, nor did it verify that subconsultant qualifications, contract terms, or pricing complied with city requirements. This lack of oversight prevents the city from ensuring fairness, competitiveness, and quality in subconsultant selection.

While the city’s 2011 “Standard Specifications for Construction General Contract Conditions” apply to the construction phase, they require written city approval of subcontractors before work begins. This is a widely accepted control designed to ensure subcontractors are qualified and terms are appropriate. Applying similar review and approval practices during the design phase is consistent with leading public-sector procurement principles, including those used at the federal level.

Without formal procedures or access to subcontracts, the city risks overpaying, receiving substandard work, or encountering payment delays and disputes. The absence of transparent, documented review weakens public trust and increases project risk.

The Mayor’s Office of the National Western Center’s contractual right to request documentation does not substitute for active oversight and enforcement of subconsultant selection. We reaffirm the finding and recommendation that the office develop and enforce formal procedures for subconsultant selection and approval.

Auditor’s addendum to agency response for Recommendation 1.6

The Mayor’s Office of the National Western Center says it implemented an independent cost estimate process and that the estimate used was unbiased and separate from the construction manager/general contractor’s estimate. However, the cost estimator, Rider Levett Bucknall Ltd., was subcontracted to Populous, the prime consultant. Because the estimator was selected and paid through Populous, it was not independent.

Office leaders did not participate in selecting the estimator and did not perform an independent estimate to evaluate design proposals. Instead, they said they compared multiple cost proposals to judge reasonableness, which is not a substitute for a formal, third-party review. 

Leading practices from the state’s construction manager/general contractor manual, the city’s guidance, and the Federal Acquisition Regulation all recommend an independent cost estimator to ensure pricing is fair and objective. The state’s manual was available when the contract was procured and is widely used by public agencies. It makes clear that cost estimators should not be financially or contractually tied to the firm whose costs they are reviewing.

By relying on a cost estimator hired through Populous, the Mayor’s Office of the National Western Center compromised the objectivity of cost validation. This increased the risk that costs were inflated and not subject to adequate oversight.

We reaffirm our finding and recommendation.

Auditor’s addendum to agency response for Recommendation 1.7

The Mayor’s Office of the National Western Center says it followed and continues to follow the city’s fiscal rules. However, this does not address the core issue.

As documented in the audit, Fiscal Accountability Rule 1.2 clearly says Workday must be used to manage and store all financial transactions and supporting documentation to ensure the integrity and validity of data.

The office’s belief that it is not responsible for ensuring Fiscal Accountability Rule 1.2 is followed resulted in the bulk of critical financial documents not being secured in Workday. The overly simplistic solution proposed by the office of informing Transportation & Infrastructure of the issue ignores the fundamental intent of Fiscal Accountability Rule 1.2: to memorialize critical financial documents by agencies closest to their creation and to ensure the city can benefit from them for decades to come.

The belief that this rule is not in the purview of the office exposed the city to document integrity issues and the potential loss of critical financial documents that will be relevant well beyond the completion of this project or the life of the office.

We reaffirm our finding and recommendation.

Auditor’s addendum to agency response for Recommendation 1.8

The Mayor’s Office of the National Western Center says it enforced contract requirements and followed the city’s prompt payment ordinance. However, this does not address the core issue.

As documented in the audit, Populous delayed submitting more than 200 subconsultant invoices by over 90 days. These delays affected nearly $3 million in labor payments and created financial strain for subconsultants. On average, it took 82 days to process an invoice, with one taking nearly a full year.

Although the office eventually issued a formal “Notice of Concern” in October 2022, this was almost two years after the delays began in December 2020. By that point, some invoices were already eight months overdue with only about $192,000 in subconsultant payments being processed. The office approved a one-time catch-up invoice, but delays continued. The office also acknowledged that it lacked a direct contractual relationship with subconsultants and could not enforce invoice timelines.

This hands-off approach, combined with the office’s reliance on Populous to manage invoice processing, resulted in repeated late payments and weakened oversight.

The issue is not whether the city eventually paid invoices after receiving them. It is that the office did not have sufficient controls in place to ensure subconsultants were paid promptly in the first place.

In addition, the office’s disagreement with this recommendation effectively acts as a warning to all future subconsultants that the city will not have their backs should they work on a city funded project through a prime contractor. This disagreement will have both direct and indirect impacts on relationships between the city and subconsultants for the foreseeable future.

This disagreement exposes the city to reputational harm, potential cost increases, and potentially reduced competition on future projects.

We reaffirm our finding and recommendation.

Auditor’s addendum to agency response for Recommendation 1.9

The Mayor’s Office of the National Western Center says it disagrees with disabling dormant users as their future input may be needed later in the project. The office also disagrees that the ability to share data from Procore with non-users outside of Procore via links presents the risk of inappropriate data disclosures.

However, these disagreements miss the core risk that both issues are symptoms of the reported root cause: the lack of formalized system governance. Both issues the office disagrees with can and should be formally authorized by office leaders by using a governance framework.

Governance frameworks recommend developing policies and procedures for IT systems that address matters like risk assessment and acceptance. Furthermore, governance frameworks also outline how managers can use formal processes in accepting risks they deem acceptable.

Because no governance framework was used to establish policies and procedures for accepting these risks, and no documentation of these decisions was available, office leaders did not establish formal criteria by which to assess their actions. Consequently, we relied on leading practices, compared to which, the office fell short.

We reaffirm our finding and recommendation.

Auditor's Letter

September 18, 2025

We audited the governance of design activity overseen by the Mayor’s Office of the National Western Center to assess whether risks associated with this $13.73 million design project were effectively managed and whether the city got what it contracted for. I now present the results of this audit.

While we found the city received what it contracted for, the audit determined the office had inadequate governance and oversight over its consultants, resulting in untimely invoice submissions and processing, reduced project transparency, and heightened risks of overpayment. My team experienced significant delays in getting requested documentation which resulted in the audit being delayed and impacted our ability to achieve our audit objectives.

By implementing recommendations for stronger governance and policies, the office will be better able to ensure effective selection and management of design consultants and subconsultants, have independent assessments of estimated costs, and ensure that invoices are submitted in a timely manner for processing as required by the contract. By implementing stronger governance over its information systems, the Mayor’s Office of the National Western Center will better protect its data from potential unauthorized access and disclosure.

I am disappointed the Mayor’s Office of the National Western Center chose to disagree with seven of our nine recommendations that would clearly improve governance and transparency over the completion of this expensive and complicated revitalization program. Further explanation is in the Auditor’s Addendums that accompany these recommendations.

This performance audit is authorized pursuant to the City and County of Denver Charter, Article V, Part 2, Section 1, “General Powers and Duties of Auditor.” We conducted this performance audit in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives.

We appreciate the leaders and team members in the Mayor’s Office of the National Western Center who shared their time and knowledge with us during the audit. Please contact me at 720-913-5000 with any questions.

Denver Auditor's Office

Auditor's Signature
Timothy O'Brien, CPA, Auditor


Timothy O'Brien Official Headshot

AUDITOR TIMOTHY O'BRIEN, CPA
Denver Auditor


Denver Auditor's Office

201 W. Colfax Ave. #705 Denver, CO 80202
Emailauditor@denvergov.org
Call: 720-913-5000
Follow us on Facebook     Connect with us on Twitter

Auditors Office Logos for Footer: Denver Auditor, Denver Labor