An existing church (2 stories) is undergoing a renovation (of 75,000 sq. ft.) and an addition (of 20,000 sq. ft.). The renovation scope includes:
- Lighting retrofits
- HVAC system upgrades
- Window replacements
The addition scope includes:
- A new wing
- Additional parking
The existing portion of the project must comply with the alterations section. The new portion of the project is an addition, so it will comply with the additions section.
Denver Energy Code Compliance
To comply with the Denver Energy Code, the project must comply with section C503 for the alteration and C502 for the addition. Each portion of the project has the option to comply with the energy code via the prescriptive path OR one of the performance pathways:
Alteration
- Prescriptive:
-
- Altered portions of the building must comply with the applicable requirements of sections C402, C403, C404, C405, and C408, as required per C503.2 through C503.5
- Unaltered portions of the building are not required to comply
- Performance:
-
- Follow C407 OR Appendix SE plus mandatory requirements. The energy target has a 10% additional allowance
- Unaltered portions of the building are modeled as existing conditions if known in the baseline and proposed models per C503.1.1
Addition
- Prescriptive:
-
- The addition must comply with the applicable requirements of sections C402, C403, C404, C405, C406, and C408, as required per C502.3
- Performance:
-
- Follow C407 OR Appendix SE plus mandatory requirements
If any of the space heating or service water heating equipment included in the project scope is gas-fired warm air furnaces, unitary air conditioners or condensing units serving a heated space, gas-fired storage or instantaneous water heaters, the project must comply with sections C503.3.2, C503.3.3 and/or C503.4.1.
Under the performance path, if the addition by itself cannot comply, the addition and alteration can be combined. The project team can modify one or more existing components as a trade-off to meet compliance requirements.
Regardless of which compliance path the project team chooses, the addition must comply with air leakage testing requirement (C402.5). The new parking lot must comply with electric vehicle supply equipment requirement (C405.13).
Green Building Ordinance Compliance
The alteration does not require a roof permit and the addition is less than 25,000 sq. ft. Neither part of this project has to comply with the Green Buildings Ordinance.
2022 Denver Green Code Compliance
The area of the addition is not 50% or more of the GSF and does not meet the definition of “major renovations, commercial.” However, the alterations project meets the definition of a “major renovation, commercial” because it is assumed to be a level 3 alteration for purposes of this example. Therefore, the project must comply with the limited mandatory use provisions of the 2022 Denver Green Code per section 101.4.1 for Limited Mandatory Use.
Energize Denver Compliance
Because the building was larger than 25,000 sq. ft. before the addition, it is subject to the Energize Denver annual Benchmarking requirements and Building Performance Standards. The team should investigate how the alteration and addition will affect the building's Energy Use Intensity and whether it should pursue any Alternate Compliance Options. Because of the larger square footage and the significant nature of the scope, the project should evaluate the Energize Denver 2030 target for Energy Use Intensity (EUI in kBtu/sf) and any applicable interim EUI requirements early in the design process. From the Energize Denver Technical Guidance, worship facility has a 2030 target of 42.1 kBtu/sf. The project team should make a plan for compliance that may include:
- Energy efficiency upgrades
- Partial or full electrification
- Installation of on-site PV
- Energy modeling