Quick Permits

Quick permits are trade-specific permits that can be issued without the need for a plan review. This page outlines the types of work eligible for a quick permit. Please note, most projects CANNOT be permitted as a quick permit, including structural work. A quick permit may only be issued for specific work. Any quick permit issued based on false statements or misrepresentations may be revoked.

ATTENTION: Beginning March 1, 2023, select gas-fired heating and cooling equipment will not be eligible for a quick permit. These projects must be reviewed before a permit can be issued. See details in the Boiler, Mechanical, and Plumbing sections below. 

Landmarks

Landmarks & historic districts

Roof permits and any other quick permits involving exterior work on an individual landmark or within a historic district cannot be issued online via e-permits. For these locations, submit via email after receiving approval from Landmark Preservation.

How to apply

For minor work requiring quick permits but introducing little to no visible change to a historic structure or property:

Quick review approvals may be issued by Landmark Preservation for the following existing exterior features providing that the applicable design guidelines and standards are met:

  • Rear-yard decks and porches (must demonstrate no change in size, height, materials and ornament)
  • Rear-yard fences (no change in height, openness, and materials)
  • 1-2 flat profile skylights on rear- or side-facing roofs
  • Sheds not on foundations (less than 100 square feet)
  • Exterior HVAC work (no change in geometry, demand, or materials)
  • Simple exterior electrical or mechanical work that is not visible from the public street
  • Reroofing (no change in materials, color, or installation pattern)

For more significant alterations, visit the Landmark Design Review webpage for guidelines and instructions on how to apply.

Boiler & Commercial A/C

What is allowed

Single-family and duplex structures and garages:

  • Baseboard heating
  • Boilers, hot water or steam (cast iron, steel, low-pressure)
  • Heat exchangers
  • Piping (gas, steam, or hot water)
  • Potable hot water (over 200,000 BTU)
  • Radiant heating
  • Residential A/C

Multifamily and commercial structures:

Like-for-like replacements of the following — no new installs — and the replacement does not have a change in geometry, demand, or material. *Starting March 1, 2023, select gas-fired equipment (starred below) will not be eligible for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

  • Baseboard heating
  • Boilers, hot water or steam (cast iron, steel, high-pressure, low-pressure)
  • Commercial pool heater
  • Compressor, condenser, or direct expansion units*
  • Heat exchangers
  • Piping (fuel oil, process, gas, hot water, steam)
  • Potable hot water heaters*
  • Pressure vessels
  • Radiant heating
  • Refrigeration with condenser water piping, refrigerant piping, split system*
  • Roof-top units*

What is not allowed

The boiler and commercial A/C items listed below CANNOT be permitted under a quick permit. Plans uploaded for review must be signed and stamped by a licensed design professional or professional engineer. Watch a 3 minute video on how to submit your Building Log application in e-permits for the following projects:

  • Walk-in coolers/freezers
  • Chillers
  • Cooling towers
  • Incinerators
  • Crematories
  • Oil burner systems
  • Compressor, condenser, or direct expansion units that serve a heated space**
  • Gas-fired potable hot water heaters**
  • Gas-fired roof-top units**
  • Split system A/C units that serve a heated space**

**Starting on March 1, 2023, compressor, condenser, or direct expansion units that serve a heated space, split system A/C units that serve a heated space, gas-fired potable hot water heaters, and gas-fired roof-top units for commercial and multifamily buildings will not be able to apply for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

Existing building electrification requirements

Starting on March 1, 2023, compressor, condenser, or direct expansion units that serve a heated space, split system A/C units that serve a heated space, gas-fired potable hot water heaters, and gas-fired roof-top units for commercial and multifamily buildings will not be able to apply for a quick permit. Select the Building Log application in e-permits and upload the following information for review:

  1. Application for a boiler and commercial A/C permit(PDF, 783KB), and
  2. One of the following is required when replacing a compressor, condenser, or direct expansion unit that serves a heated space, a split system A/C unit that serve a heated space, a gas-fired potable hot water heater, and two of the following is required when replacing a gas-fired roof-top unit:
    • Electrification Feasibility Report, and/or
    • Gas leak testing of all piping connected to the gas meter per the 2022 Denver Energy Code Section C503.3.3, item 3, (for space heating equipment) or Section C503.4.1, item 2, (for water heater projects), and/or
    • A report prepared, signed, and stamped by a licensed design professional or professional engineer showing that the equipment is the correct size per the 2022 Denver Energy Code Section C403.3.1 (not for water heater projects)

Watch an ~5 minute tutorial video

View the FAQ

Learn more about Denver's electrification requirements

Electrical

What is allowed

Single-family and duplex structures and garages:

The following electrical work can be issued as a quick permit only if the utility service is rated 200 Amps or less. Applies only to single-phase services, not three-phase services.

  • New utility service installation rated 200 Amps or less
  • Utility service upgrade rated 200 Amps or less
  • New or replacement panels and subpanels
  • Interior/exterior wiring or rewiring
  • Electric vehicle chargers
  • GFCI outlets
  • Appliances
  • Disconnect switches
  • Any other equipment or appliance with a rated voltage of over 50 volts
  • New or replacement mechanical equipment
  • Temporary service with utility meter for construction power, provided the service is rated 200 Amps or less
  • Solar PV systems with utility service of 200 Amps or less AND kW DC rating of less than 10. To see if your PV project qualifies for a quick permit, review the new SolarAPP+ permit eligibility requirements.

Multifamily and commercial structures:

  • Fewer than 10 new circuits, where each circuit does not exceed 20 Amps at 120 or 277 Volts
    • All new circuits must be single pole
  • Relocating lights within the same room or space, with no new lights added

What is not allowed

The electrical items listed below CANNOT be permitted under a quick permit. Unless noted differently below, electrical plans uploaded for review must be signed and stamped by a professional electrical engineer. Engineered plans must contain a one-line diagram, load calculations, fault current calculations, site and/or floor plans, scope of work narrative, code references, and a verifiable digital signature and stamp of the electrical engineer. Watch a 3 minute video on how to submit your Building Log application in e-permits for the following projects:

  • Solar photovoltaic (PV) systems
    • Some single-family and duplex see new SolarAPP+ permit requirements 
    • All commercial and multifamily PV systems, regardless of kW DC rating, will require stamped and signed engineered plans
  • Feeders and raceways, new or replacements
  • Transformers
  • Changes to existing grounding systems
  • Other electrical distribution (UPS, transfer switches, switchboards, etc.)
  • New, replacement, or upgraded services over 200 Amps for single-family/duplex
  • New, replacement, or upgraded services (of any rating) for multifamily/commercial
  • Panels and subpanels
  • All electrical work for single-family/duplex, including new/replacement panels, subpanels, etc., where the utility service is rated over 200 Amps
  • Temporary services for multifamily/commercial structures, including temporary construction services
  • Special events lasting longer than 72 hours
  • Electric vehicle charging stations
  • Any other electrical work, equipment, or appliance installations not listed above

Mechanical

What is allowed

Single-family and duplex structures and garages:

  • Residential A/C
  • Compressor units
  • Ductwork
  • Evaporative cooling units
  • Exhaust systems
  • Fireplaces (prefab metal, gas log, gas piping, gas vent)
  • Forced air heating systems
  • Gas piping
  • Make-up air units
  • Range hoods
  • Roof-top units (10 tons or less)
  • Through-wall heaters
  • Unit heaters
  • Ventilating systems
  • Water heaters

Multifamily and commercial structures:

Like-for-like replacements of the following — no new installs — and the replacement does not have a change in geometry, demand, or material. *Starting March 1, 2023, select gas-fired equipment (starred below) will not be eligible for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

  • Compressor, condenser, or direct expansion units*
  • Ductwork
  • Evaporative cooling units
  • Exhaust systems
  • Fireplaces (prefab metal, gas log, gas piping, gas vent)
  • Forced air heating systems*
  • Gas piping
  • Make-up air units*
  • Medical gas
  • Roof-top units*
  • Through-wall heaters
  • Unit heaters
  • Ventilating systems
  • Water heaters*

Ensure that replacement equipment meets current energy code efficiency standards, which will need to be verified upon inspection.

What is not allowed

The mechanical items listed below CANNOT be permitted under a quick permit. Plans uploaded for review must be signed and stamped by a licensed design professional or professional engineer. Watch a 3 minute video on how to submit your Building Log application in e-permits for the following projects:

  • Duct, stock, and vapor removal systems
  • Repair/replace of equipment for which the system was not originally designed (e.g., replacing equipment under a kitchen hood for which the hood was not originally designed)
  • Repairs/replacements that are not like-for-like or that require other associated upgrades (e.g., replacing toilet fixtures in a commercial restroom that may require ADA improvements, or replacing gas-fired equipment with higher efficiency equipment that might also require a new chimney liner or separate flue)
  • Compressor, condenser, or direct expansion units that serve a heated space**
  • Gas-fired forced air heating systems**
  • Gas-fired roof-top units**
  • Gas-fired water heaters**
  • Gas-fired make-up air units**

**Starting on March 1, 2023, compressor, condenser, or direct expansion units that serve a heated space, gas-fired forced air heating systems, gas-fired roof-top units, gas-fired water heaters, and gas-fired make-up air units for commercial and multifamily buildings will not be able to apply for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

Existing building electrification requirements

Starting on March 1, 2023, compressor, condenser, or direct expansion units that serve a heated space, gas-fired forced air heating systems, gas-fired roof-top units, gas-fired water heaters, and gas-fired make-up air units for commercial and multifamily buildings will not be able to apply for a quick permit. Select the Building Log application in e-permits and upload the following information for review:

  1. Application for a mechanical permit(PDF, 787KB), and
  2. One of the following is required when replacing a gas-fired water heater or an air conditioning unit, and two of the following is required when replacing a gas-fired furnace or a gas-fired roof-top unit:
    • Electrification Feasibility Report, and/or
    • Gas leak testing of all piping connected to the gas meter per the 2022 Denver Energy Code Section C503.3.3, item 3, (for space heating equipment) or Section C503.4.1, item 2, (for water heater projects), and/or
    • A report prepared, signed, and stamped by a licensed design professional or professional engineer showing that the equipment is the correct size per the 2022 Denver Energy Code Section C403.3.1 (not for water heater projects)

Watch an ~5 minute tutorial video

View the FAQ

Learn more about Denver's electrification requirements

Plumbing

What is allowed

Single-family and duplex structures and garages:

  • Back flow preventers
  • Dishwasher
  • Drinking fountain
  • Floor drain
  • Garbage disposals
  • Gas piping outlets
  • Showers, tubs, and sinks
  • Swimming pool piping
  • Washer
  • Water closets and urinals
  • Water heaters
  • Water service
  • Water softeners 

Multifamily and commercial structures:

Like-for-like replacements of the following — no new installs — and the replacement does not have a change in geometry, demand, or material. *Starting March 1, 2023, select gas-fired equipment (starred below) will not be eligible for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

  • Back flow preventers
  • Dishwasher
  • Drinking fountain
  • Fire lines (New fire lines can be issued as a quick permit but are not yet available in e-permits. Please continue to apply via email for this in the meantime.)
  • Floor drain
  • Garbage disposals
  • Gas piping outlets
  • Showers, tubs, and sinks
  • Swimming pool piping
  • Washer
  • Water closets and urinals
  • Water heaters*
  • Water service (New water service lines can be issued as a quick permit but are not yet available in e-permits. Please continue to apply via email for this in the meantime.)
  • Water softeners

What is not allowed

The plumbing items listed below CANNOT be permitted as a quick permit. Plans uploaded for review must be signed and stamped by a licensed design professional or professional engineer. Watch a 3 minute video on how to submit your Building Log application in e-permits for the following projects:

  • Grease interceptors
  • Swimming pool heaters
  • Gas-fired water heaters**

**Starting on March 1, 2023, like-for-like gas-fired water heaters for commercial and multifamily structures will not be able to apply for a quick permit. Refer to the existing building electrification requirements dropdown for application instructions, or watch an ~5 minute tutorial video.

Existing building electrification requirements

Starting on March 1, 2023, like-for-like gas-fired water heaters for commercial and multifamily structures will not be able to apply for a quick permit. Select the Building Log application in e-permits and upload the following information for review:

  1. Application for a plumbing permit(PDF, 665KB), and
  2. One of the following:

Watch an ~5 minute tutorial video

View the FAQ

Learn more about Denver's electrification requirements

Roofing & Siding

What is allowed

A roof permit is always applied for separately from the general construction permit, even for new construction. All roofing/siding work on individual landmarks or buildings within a historic district must be first approved by Landmark Preservation.

  • New roofs
  • Roof repair/replacement - All repairs that are more than 10% of the roof square footage or two roof squares (whichever is smaller) require a roof permit
  • New roof penetrations (e.g., skylights, roof-top units, pipes, solar)
  • Exterior wall coverings
  • Blown-in insulation
  • Soffit/fascia work

What is not allowed

The roofing/siding items listed below CANNOT be permitted as a quick permit. Watch a 3 minute video on how to submit your Building Log application in e-permits for the following projects:

  • Roof permits for any commercial or multifamily building 25,000 square feet or more (these projects are subject to the Green Building Ordinance)
  • Green roofs
  • Changing the structural framing of the roof (e.g., going from a flat to a pitched roof) or structural repair

Other Permit Types

Other permits that may be required

A permit from WastewaterZoning, or the Fire Department may be required depending on your scope of work. Permits to use the right-of-way or for street closures are issued by the Department of Transportation & Infrastructure.

Work exempt from building permits

Some projects do not require building permits. See more detailed information in the Denver Building and Fire Code, Section 130.3 Exempted Work.


Ready to Apply?

Visit e-permits to apply for permits, view e-permits tutorial videos, FAQs, and more. Once signed into the e-permits portal, go to "Apply for a Permit" under the "Development Services" section and follow the prompts.

Go to e-permits now