April 29, 2022
Status: Work on the junction structure—at the Colorado Blvd. / E. 17th Ave. intersection on the west side—is underway. That structure will connect the 96” inch stormwater pipe to the 9’ x 9’ box culverts. Crews are set to tie into the end of the tunnel pipe in E. 17th Ave. Parkway and begin the open-cut placement of the 96” pipe in Albion. Work on curb / gutter and medians on the east side along E. 17th Ave. Parkway continues. Electrical work for the light poles at the Colorado Blvd. / E. 17th Ave. intersection is also underway with pole and light installation scheduled within the next two weeks.
Trash Pickup: There may be some upcoming changes to trash pickup locations on the east side. You will be contacted individually if your location needs to be changed. If your trash service does not get picked up, please call our hotline or send us an email and we will help get that resolved.
Current Impacts: Watch for some sidewalk closures on the east side of Colorado—along E. 17th Ave. Parkway—during curb and gutter work. The milling and overlay of Colorado Blvd. in the middle of May will require some lane closures of Colorado Blvd. We will keep you posted as we get closer.
E. 17th Avenue—from Jackson Street to Colorado Blvd.—will be closed until early June. East 17th Avenue Parkway westbound—from Bellaire Street to Colorado Blvd.—is closed. Both eastbound routes of E. 17th Ave. Parkway are closed from Colorado Blvd. to Albion.
Be Careful!: We have heavy equipment working on both sides of Colorado Blvd. Please use extreme caution when walking / driving / biking near the site.
Rider Alert / RTD Route 20 Changes: RTD’s route #20 has changed as a result of this project. Please check the RTD route websites for details: Route 20
Garfield Bike Path Work: The bike path across E. 17th Ave. into City Park at Garfield Street is nearing completion. Garfield Street—just west of our project—remains closed. Please contact Jacob Hurley at jacob@circuitmedia.com / (515) 451-7494 with any questions or concerns regarding that project.
Questions?: Just let us know. Please email, call or text the hotline if you have any questions or concerns.
Have a great weekend!
April 21, 2022
Status: The installation of the 9’ x 9’ box where the tunnel pit was located—on the west side of the Colorado Blvd./E. 17th Ave. intersection—is finishing up. Work on the junction structure at that same location will continue for the next couple of weeks. That structure will connect the 96” inch pipe to the 9’ x 9’ boxes. The placement of the 96” pipe in Albion will start next week. Crews are also working on curb / gutter, and medians on the east side along E. 17th Ave. Parkway. The electrical prep work for light poles at the Colorado Blvd. / E. 17th Ave. intersection is happening this week, and we expect pole and light installation within the next two weeks. We will be milling and paving sections of the Colorado Blvd / E. 17th Ave. intersection the first week of May.
Trash Pickup: You will be contacted individually if trash pickup locations need to be changed. If your trash service does not get picked up, please call our hotline or send us an email and we will help to get that resolved.
Current Impacts: Watch for some sidewalk closures on the east side of Colorado—along E. 17th Ave. Parkway—during curb and gutter work. The milling and overlay of Colorado Blvd. during the first week of May will require a closure of Colorado Blvd. We will keep you posted on details.
E. 17th Avenue—from Jackson Street to Colorado Blvd.—will be closed until early June. East 17th Avenue Parkway westbound—from Bellaire Street to Colorado Blvd.—is closed. Both eastbound routes of E. 17th Ave. Parkway are closed from Colorado Blvd. to Albion.
Use Caution!: We have lots of work ongoing on both sides of Colorado Blvd., so please be extremely careful around the project area.
Rider Alert / RTD Route 20 Changes: RTD’s route #20 has changed as a result of this project. Please check the RTD route websites for details: Route 20
Garfield Bike Path Work: Work on the bike path across E. 17th Ave. into City Park at Garfield Street is still ongoing. Garfield Street—just west of our project—remains closed. Please contact Jacob Hurley at jacob@circuitmedia.com / (515) 451-7494 with any questions or concerns regarding that project.
Reach Out: If you have any questions, Please email, call or text the hotline if you have any questions or concerns.
Enjoy the weekend!
April 15, 2022
Status: With all tunneling equipment off the site, the focus is on laying the 9’ x 9’ box where the tunnel pit was located—on the west side of the Colorado Blvd./E. 17th Ave. intersection. That work will continue into next week. Crews will also begin work on the junction structure next week at that same location. This structure will connect the 96” inch pipe to the 9’ x 9’ boxes. Once the 9’ x 9’ boxes are in place, that crew will jump across Colorado Blvd. to start to work on the placement of the 96” pipe in the E. 17th Ave. Parkway and Albion area. More miscellaneous stormwater work includes manholes and inlets in the eastbound lanes of E. 17th Ave. Parkway at Colorado Blvd. Work on traffic signals at the Colorado Blvd./E. 17th Ave. intersection is ongoing.
Trash Pickup: If we need to alter trash pickup locations, you will be contacted individually. If your trash service does not get picked up, please call our hotline or send us an email and we will help to get that resolved.
Current Impacts: E. 17th Avenue—from Jackson Street to Colorado Blvd.—will be closed until early June. East 17th Avenue Parkway westbound—from Bellaire Street to Colorado Blvd.—is closed. Both eastbound routes of E. 17th Ave. Parkway are closed from Colorado Blvd. to Albion.
Heavy Truck Traffic Warning: There’s a lot going on out there. Please use caution when you are out and about near the project.
Rider Alert / RTD Route 20 Changes: RTD’s route #20 has changed as a result of this project. Please check the RTD route websites for details: Route 20
Garfield Bike Path Work: Work on the bike path across E. 17th Ave. into City Park at Garfield Street is still ongoing. Garfield Street— just west of our project—remains closed. Please contact Jacob Hurley at jacob@circuitmedia.com / (515) 451-7494 with any questions or concerns regarding that project.
Have a Concern?: It’s easy to reach us. Please email, call or text the hotline if you have any questions or concerns.
More good progress was made this week, with work on both sides of Colorado Blvd!
April 8, 2022
Status: Last weekend’s northbound closure of Colorado Blvd. was a success, with crews opening the roadway on Sunday—well ahead of schedule. Tunneling is now complete and the tunnel head was pulled out of the pit this morning. Crews are now cleaning out the tunnel and all tunneling equipment should be off the site by early next week. Truckloads of pipe are now starting to arrive for placement in Albion Street. That work is scheduled to begin the end of the week of April 18th. Work on traffic signals at the intersection will start up next week. Watch for curb / gutter work on the medians at Colorado and E. 17th Ave. Parkway.
Trash Pickup: There may be some upcoming changes in trash pickup locations as the job progresses—you will be contacted individually if things should change. If your trash service does not get picked up, please call our hotline and we will help to get that resolved.
Current Impacts: E. 17th Avenue—from Jackson Street to Colorado Blvd.—will be closed until early June. East 17th Avenue Parkway westbound—from Bellaire Street to Colorado Blvd.—is closed. Both eastbound routes of E. 17th Ave. Parkway are closed from Colorado Blvd. to Albion. See the new impact map above for details.
Be Careful!: We have tunneling equipment moving off the site and truckloads of pipe moving in, so please use caution when you are out and about near the project.
Rider Alert / RTD Route 20 Changes: RTD’s route #20 has changed as a result of this project. Please check the RTD route websites for details: Route 20
Garfield Bike Path Work: The bike path across E. 17th Ave. into City Park at Garfield Street is ongoing. Garfield Street— just west of our project—remains closed for this work. Please contact Jacob Hurley at jacob@circuitmedia.com / (515) 451-7494 with any questions or concerns regarding that project.
Questions?: We have answers! Please email, call or text the hotline if you have any questions or concerns.
Lots of good progress this past week!
April 1, 2022
Status: Tunneling operations are winding down, and the tunnel is complete to just short of Albion Street. By the end of next week, all of the tunneling equipment will be off the site. At that point, the crew will begin to stage the last 50’ of the 9’ x 9’ concrete boxes that will be placed up to the entrance of the tunnel on the west side. That work should occur during the week of April 11th. Sidewalk work on the SE corner of the park is complete and that area is now fully open to pedestrians. Traffic signal upgrades at the intersection are coming soon.
Northbound Colorado Blvd. Closure This Weekend, April 1- 4: We are set for the next complete closure of northbound Colorado Blvd. this weekend, April 1 - 4. The closure will be in place from the north side of Colfax Ave. to the south side of E. 18th Ave. The closure will begin at 9 PM on April 1st—continuing until approximately 5 AM on Monday morning, April 4th, if not before. The Montview and E. 23rd Ave. intersections will not be affected. Detour signs and message boards will be in place.
City Park, City Park Golf Course, Denver Zoo and Denver Museum of Nature and Science will all be accessible from Colorado Blvd. and 23rd Ave. during both closures. Delays should be anticipated. Crews will install sound barriers on Friday night before work begins. We will work 24 hours a day during the weekend to ensure that we finish as quickly as possible.
This closure is weather dependent — we will keep you posted.
Current Impacts: E. 17th Avenue—from Jackson Street to Colorado Blvd.—will be closed until early June. East 17th Avenue Parkway westbound—from Albion to Colorado Blvd.—remains closed.
Caution!: With the tunneling equipment moving off the site, the area will be even busier with truck traffic. Please use caution when driving / biking / walking around the project area.
Rider Alert / RTD Route 20 Changes: RTD’s route #20 has changed as a result of this project. Please check the RTD route websites for details: Route 20
Garfield Bike Path Work: The bike path across E. 17th Ave. into City Park at Garfield Street is looking good. Garfield Street— just west of our project—remains closed for this work. Please contact Jacob Hurley at jacob@circuitmedia.com / (515) 451-7494 with any questions or concerns regarding that project.
Need to Reach Us?: Have a question or concern? If so, please email, call or text the hotline. We will get back to you as soon as possible.
It’s all systems go with this nice weather.