16th Street Mall Project

Project Overview

16th Street Mall Project construction is complete!

An infographic showing the timeline of the 16th Street Mall renovation project
 

 

Current Project Activities

Project Closeout Activity
After construction wraps up on each block, the project team may return to complete final tasks such as inspections, adjustments, and minor touch-ups. These activities may require short-term lane closures or the use of cones or fencing around work zones. Examples of types of closeout work include:

 

Concrete Work

Crews are removing and replacing sections of concrete to correct slope issues. Work zones will be marked with caution tape and cones for safety.
An image of concrete construction work adjacent to the 16th Street project

 

Granite Paver Work

Crews are removing and replacing granite pavers along the pedestrian walkway and the bus transitway to fix uneven surfaces and improve drainage. Expect caution tape and cones around active work areas.

Image of concrete paver installation on 16th Street

 

Level of Green (LOG) Work

At intersection corners, crews are adjusting elevation of soil, refreshing the mulch, replacing plants and reinstalling railings as needed.

Image of subsurface construction work for 16th Street

 

Traffic Signal Work

Crews are accessing underground pull boxes and may use a manlift to adjust traffic signal lights. Temporary traffic control will be set up as needed.

Image of a traffic signal installation on 16th Street

 

Installation of Final Furnishings, Fixtures and Equipment

The Downtown Denver Business Improvement District (BID) installs the final furnishings, fixtures and equipment along 16th Street. The installation of the final touches, including furniture, planters, trash cans and other special elements that will introduce the New Look on 16th Street, may occur after Phase 3 of construction is complete, depending on the BID's schedule, timelines of deliveries and weather. These activities could have safety fencing or cones around them, but only in the area where crews are working. The BID will work directly with property owners to coordinate patio installations following the installation of these final touches.


The New Look

Before and After!

Before: the 16th Street Mall block and transit lanes at Larimer intersection After: the rebuilt block of the 16th street mall with new configuration and pedestrian activation spaces

The new 16th Street Mall features elements designed to help make it a desirable, engaging destination for all. Site furnishings, play features and moments of joy are being distributed up and down 16th Street in relationship to activity areas and adjacent land uses.

The ensemble of these features will work together to create attractions and moments of relaxation and fun for families, residents, visitors and workers to enjoy in the core of downtown.

Artist's illustration of the future 16th Street Mall, showing pedestrians in the amenity zone and the new granite pavers in the historic pattern

Site Furnishings

The site furnishings will be organized into three basic room types — feastlounge and arrow — to create places for a multitude of uses.

  • Feast rooms are designed with food in mind. They create space to share lunch with a friend or eat solo and catch up on your emails on a beautiful day.
  • Lounge rooms create space to slow down and stay for a bit. Visitors can take a moment to plan their next stop, downtown employees can pause in the shade for a moment between meetings and residents can enjoy the people watching for a while.
  • Arrow rooms activate an area while also creating a clear delineation of space.

These site furnishing room types will be paired with planter pots for visual color and interest and all furnishing groupings will be flexible, changeable and phased as a new evolution of place making and sensory experiences along 16th Street evolve for everyone’s enjoyment.

Play Features

Play Features

Play Features are structures designed specifically for engaging kids on 16th Street. Scan the QR code to view a 360 degree rendering of the Hive play feature.

360 Degree Rendering of Hive Play Feature

 


Project Background

The 16th Street Mall Project builds on nearly a decade of planning and community input to inform how we reconstruct and revitalize the Mall from Market Street to Broadway. The feedback and input from hundreds of community members resulted in today’s effort to rebuild 16th Street to be not just more structurally sound, but also a welcoming space where all people can gather.

Environmental Assessment

The project’s environmental phase concluded in December 2019. FTA found the project to have no significant impact on environmental resources and officially issued a “Finding of No Significant Impact” (FONSI) on Nov. 26, 2019. This marked completion of the Environmental Assessment (EA). The EA identified a Locally Preferred Alternative (LPA) to reconstruct the 16th Street Mall between Market Street and Broadway to address infrastructure, mobility, safety, and public use needs.

Finding of No Significant Impact

May 2019 EA Public Meeting

Members of the public were invited to attend public meetings to provide input on the project and EA conclusions. The same information was presented at two meetings on May 1, 2019.

FTA and the project partners reviewed and considered all comments. All comments received during the comment period will be part of the project record. Responses to all substantive comments (those that raise specific issues or concerns regarding the project or EA process, suggest new alternatives, or question or raise concerns over new impacts not addressed in the EA) will be included in the final decision document.

Environmental Clearance and Funding: Because 16th Street was built in 1982 with federal funds, any potential modifications must undergo a National Environmental Policy Act (NEPA) review and a cultural resources evaluation pursuant to Section 106 of the National Historic Preservation Act of 1966 (NHPA). Initial project funding for the Alternatives Analysis and Environmental Clearance came from Tax Increment Financing (TIF) via Denver Urban Renewal Authority (DURA) and the Federal Transit Administration (FTA). TIF requires that a design project be identified by 2020 and spent by 2022. As approved by voters, 2017 General Obligation Bonds might also be applied.


Public Engagement Archive

2022: 90% Design

In March 2022 a round of outreach was completed to accompany 90% Design and to inform stakeholders about what to expect once construction begins.

Watch the 90% design video

2021: 60% Design

In late 2021, the 16th Street Mall Project team completed another round of outreach to accompany the submittal of 60% design. This round focused on providing design updates for various amenities along 16th Street — shade structures, play elements and more. This video was recorded at one of the focus group meetings and focuses on how design of 16th Street amenities has evolved over the years, and the current design for elements along the 16th Street Mall.

Watch the 60% design video

Artists rendering of new 16th Street transit and pedestrian mall

2017-19

March 2018 Open House

On March 8, 2018, the city and RTD hosted open houses where the public could learn more, ask questions and give input on future refinement of the design. Review the open house materials:

October 2017 Open Houses

Attendees at two open house sessions learned about the 16th Street Mall, including the following:

  1. Project Overview (PDF)
  2. Existing Conditions and Environmental Resources (PDF)
  3. History of the Mall and Previous Studies (PDF)
  4. Input to Date (PDF)
  5. Proposed Alternatives and Evaluation (PDF)
  6. Next Steps (PDF)

View a summary of the October 2017 Open Houses (PDF)

July 2017 Open Houses

Attendees at two open house sessions learned about the 16th Street Mall, including the following:

  1. Project overview (PDF)
  2. Environmental process (PDF)
  3. History of the mall - previous studies (PDF)
  4. Existing conditions (PDF)
  5. Next steps (PDF)
  6. Evaluation criteria (PDF)

View a summary of Meet in the Street and the July 2017 Open Houses (PDF)