Travel and Safety Improvements at Broadway & I-25

Project Summary

DOTI is making travel and safety improvements at Broadway & I-25 that include replacing the existing at-grade southbound on-ramp to I-25 from Broadway with an elevated ramp to ease vehicle congestion and enhance safety. Other work will improve access to the I-25 & Broadway Station for people who walk and bike.

Completed Milestones

Since the project began last summer, the project has:

  • Opened new elevated on-ramp to southbound I-25 from Broadway.
  • Extended Bannock Road south of Exposition Avenue, providing access to the RTD Park-n-Ride from the north. This includes: improved lighting, landscaping and a new multi-use pathway. 
  • Completed sanitary sewer and storm sewer work throughout the area.
  • Constructed a major portion of the elevated on-ramp to southbound I-25 , including two new bridges.
  • Constructed a temporary parking lot, W. Exposition from Broadway to Bannock and elevated I-25 on-ramp across Broadway.
  • Reconstructed E. Exposition from Broadway to Lincoln and installed new traffic signals at both intersections.
  • Reconstructed east sidewalk between Ohio and Kentucky.

By Spring 2026, this project will:

  • Expand multi-use pathways for pedestrians and cyclists.
  • Connect the Broadway bike lane to the RTD Broadway station.
  • Install new traffic signals at Ohio Avenue (between Broadway and Lincoln Street) and at Broadway and Kentucky Avenue.
  • Reconstruct local streets including Lincoln, Broadway, Kentucky and Ohio.
  • Reconstruct Kentucky Avenue, combining the existing intersection with the elevated southbound on-ramp to I-25.
  • Extend bikeway from Center to Exposition.

The I-25 & Broadway Station is the second busiest in the RTD system and supports a high frequency of bus travel along the Broadway corridor, connecting Englewood to downtown Denver.

Crews work to install traffic signals throughout the project. Image taken facing southeast on Walsh, between southbound Broadway and Lincoln.

Crews pouring sidewalk along Ohio.

Multiple new fire hydrants have been installed as part of this project.
Image taken facing south and west of Broadway, between Ohio and Kentucky.

View of work on walls for the Denver Tramway Trolley Line interpretative mitigation area.

Work continues to prepare for paving of southbound lanes of Broadway. Image taken facing east on Broadway at the southbound I-25 on-ramp.

Crews performing sidewalk, curb and gutter reconstruction at north alleyway on Ohio.

Crews continue stone work near the future Denver Tramway Trolley Line interpretative mitigation area. Image taken facing west, east of Bannock at the north Broadway & I-25 RTD Station entrance.

Vehicles moving through new traffic configuration on northbound Broadway


Travel Impacts

Where: Northeast corner of Lincoln and Ohio

  • Closures of the east sidewalk on Lincoln, from Ohio to Walsh, and north sidewalk on Ohio from the alleyway to Lincoln, on the northeast corner of Lincoln and Ohio began in late March, lasting through early June 2025.
    • Please see the current pedestrian access map linked here for details.

Where: Southbound I-25 on-ramp at Broadway

  • What: Elevated on-ramp to SB I-25 opened December 20, 2024
  • Additional access to SB I-25 via Mississippi Avenue or Alameda and Kalamath.
  • See Access Map here.

Where: Southbound I-25 off-ramp at Broadway (Exit 207A)

  • What: Right lane closure
  • When: Began early June and will last through late September 2025

Where: Ohio Avenue between Broadway and Lincoln Avenue

  • What: Closed to through traffic
  • When: Began July 1, lasting through 2025

Where: Sidewalk along the east and west sides of Broadway between Kentucky and Ohio avenues

  • East sidewalk between Kentucky and Ohio Avenue reopened on Feb. 17, 2025
  • Sidewalk closure along west side of Broadway between Kentucky and Exposition avenues began July 26, 2024, lasting through 2025.

Where: Northbound and southbound Broadway between Mississippi and Center avenues

  • The number of travel lanes on Broadway within the project limits has been reduced to two lanes in each direction and will remain this way through the summer of 2025

Broadway Station Access Pedestrian Detour

For your safety, please do not travel through the active construction site.

  • To access the station from the south, follow west Kentucky.
  • To access the station from the north, follow Exposition and Bannock.

Please see the current pedestrian access map linked here for details.


Please note that there will be variable traffic patterns along Broadway for the duration of this project. All lane closures will be communicated in advance.

All project activities are weather- and site-condition-dependent, and schedules are subject to change.

Current Access to Southbound and Northbound I-25

Accessing the southbound I-25 on ramp: Drivers going south on Broadway will now turn right to access the I-25 southbound on-ramp at Ohio Avenue. Those heading north on Broadway will continue onto Walsh Place and Lincoln, turn left at Exposition and another left at Broadway. Drivers can then turn right onto the on-ramp at Ohio.

Accessing the northbound I-25 on-ramp: Northbound I-25 access remains at Lincoln for drivers on northbound Broadway. Drivers on southbound Broadway are encouraged to access I-25 using Alameda or Mississippi.

Project Schedule

Construction began summer 2023, with completion expected spring 2026. Crews will be on-site between 7:00 a.m. and 5:00 p.m., Monday–Friday, with occasional weekend work to lessen travel impacts. Sidewalk and roadway impacts will be communicated weekly.


Project Map