Travel and Safety Improvements at Broadway & I-25

Project Summary

DOTI is making travel and safety improvements at Broadway & I-25 that include replacing the existing at-grade southbound on-ramp to I-25 from Broadway with an elevated ramp to ease vehicle congestion and enhance safety. Other work will improve access to the I-25 & Broadway Station for people who walk and bike.

Completed Milestones

Since the project began last summer, the project has:

  • Extended Bannock Road south of Exposition Avenue, providing access to the RTD Park-n-Ride from the north. This includes: improved lighting, landscaping and a new multi-use pathway. 
  • Completed sanitary sewer and storm sewer work throughout the area.
  • Constructed a major portion of the elevated on-ramp to southbound I-25 , including two new bridges.
  • Construction of a temporary parking lot, W. Exposition from Broadway to Bannock and elevated I-25 on-ramp across Broadway.
  • Reconstruction of E. Exposition from Broadway to Lincoln and installation of new traffic signals at both intersections.

By Spring 2026, this project will:

  • Expand multi-use pathways for pedestrians and cyclists.
  • Connect the Broadway bike lane to the RTD Broadway station.
  • Install new traffic signals at Ohio Avenue (between Broadway and Lincoln Street) and at Broadway and Kentucky Avenue.
  • Reconstruct local streets including Lincoln, Broadway, Kentucky and Ohio.
  • Reconstruct Kentucky Avenue, combining the existing intersection with the elevated southbound on-ramp to I-25.
  • Extension of the bikeway from Center to Exposition.
  • Finishing elevated on-ramp to southbound I-25 to Broadway.

The I-25 & Broadway Station is the second busiest in the RTD system and supports a high frequency of bus travel along the Broadway corridor, connecting Englewood to downtown Denver.

Travel Impacts

Where: Southbound I-25 off-ramp at Broadway (Exit 207A)

  • What: Right lane closure for future road widening
  • When: Began Tuesday, Aug. 6, lasting through late 2024

Where: Ohio Avenue between Broadway and Lincoln Avenue

  • What: Closed to through traffic
  • When: Began Monday, July 1, lasting through 2025
  • Notes: 
    • Access to northbound I-25 and Lincoln will remain from northbound Broadway
    • Access to northbound I-25 and Lincoln will remain from westbound Ohio Avenue
    • No westbound access from Lincoln to Ohio Avenue and southbound Broadway
      • Please use Exposition to access Broadway
    • No access from northbound I-25 off-ramp to westbound Ohio Avenue and southbound Broadway
      • Use Exposition to access Broadway
Map of closures on Ohio Avenue between Broadway and Lincoln Avenue

Where: Southbound I-25 on-ramp at Broadway

  • What: Permanent full closure
  • When: Began mid-June for utility work
  • Notes:
  • The new southbound I-25 on-ramp with access via Ohio Avenue is expected to open by the end of 2024.
  • The existing at grade on-ramp will be replaced with new, elevated on-ramp in the future
  • Access SB I-25 via Mississippi Avenue or Alameda and Kalamath. Detour map here.

Where: Sidewalk along the east and west sides of Broadway between Kentucky and Ohio avenues

  • What: Construction will cause restricted access, alternate routes suggested
  • When: Began Friday, July 26, lasting through the fall of 2024
  • Note: Follow signage and do not walk through the construction zone.
Map of sidewalk detour along the east and west sides of Broadway between Kentucky and Ohio Avenues

Where: Northbound and southbound Broadway between Mississippi and Center avenues

  • The number of travel lanes on Broadway within the project limits has been reduced to two lanes in each direction and will remain this way through the summer of 2025.

Broadway Station Access Pedestrian Detour

For your safety, please do not travel through the active construction site.

  • To access RTD Broadway Station from the south, follow west Kentucky
  • To access RTD Broadway Station from the north, follow Exposition and Bannock

Please note that there will be variable traffic patterns along Broadway for the duration of this project. All lane closures will be communicated in advance.

All project activities are weather- and site-condition-dependent, and schedules are subject to change.

Project Updates and Schedule

Construction began summer 2023, with completion expected spring 2026. Crews will be on-site between 7:00 a.m. and 5:00 p.m., Monday–Friday, with occasional weekend work to lessen travel impacts. Sidewalk and roadway impacts will be communicated weekly.


Concrete on guardrails along future southbound I-25 on-ramp. Image taken facing east, south of I-25, east of Broadway.

Concrete on guardrails along future southbound I-25 on-ramp.

Progress on new, elevated southbound on-ramp nearing completion.
Image taken facing west, at Ohio Avenue, west of Broadway.

Progress on new, elevated southbound on-ramp nearing completion.

Southbound I-25 access via Broadway is permanently closed.
(Image taken facing northeast at southbound I-25 on-ramp at Broadway)

Road closure signs and cones at the intersection of Kentucky and the southbound interstate entrance

Ohio Avenue between Broadway and Lincoln Avenue is closed to through traffic. (Image taken facing east on Ohio Avenue at Broadway)

road closure signage at Broadway and Ohio intersection


Project Map