Cherry Creek North (CCN)

The City and County of Denver hosts a monthly construction coordination meeting with key contractors working in the CCN area: N University Blvd to N Steele St and 1st Ave to 3rd Ave.

The purpose of the meeting is to work with contractors to cross-check and coordinate specific street projects within the CCN area and to not have streets inaccessible to motorists/pedestrians at any one time.  Parking may be limited by these projects and lane closures are expected.

A monthly construction schedule of projects and locations is outlined below.  Ongoing construction projects are also listed.  When completion dates are known they will be noted. 

NOTE:  For contractors and others wishing to do work or close streets in the CCN area, you are required to attend the CCN Coordination Meeting prior to starting your work. These meetings are to assist with coordinating all the various CCN Projects. 

Meetings will be held every other month on the third Thursday at 10:00 a.m.

Please contact info@cherrycreeknorth.com for an invitation to the monthly meeting.

Work Times - Unless noted, all work times are 8:30 a.m. to 3:30 p.m.


Cherry Creek Coordination: 1/31/2025

CCN - Cherry Creek Coordination 1/31/2025(PDF, 609KB)

START END COMPANY LOCATION CLOSURE
1/1/2025 1/31/2025 CCN-BID Fillmore Street (1st Ave to 2nd Ave) Master Permit Refer to IGA 2025 Event Calendar for Revised Event Dates. 2nd Avenue (Detroit to Milwaukee) full sidewalk Cherry Creek North Fillmore Plaza Annual Permit - IGA 2025
1/29/2025 1/31/2025 ADCON Signs Advertising Concepts, Inc. dba ADCON Signs - 263 Josephine St - N University (E Cherry Creek Drive N to E 1st Ave) Sign Install Sign Install
2/1/2025 2/1/2025 Duffy Crane Duffy Crane and Hauling - 2800 E 2nd Ave - N Detroit St (E 1st Ave to E 2nd Ave) 01 Permit Crane Crane Service
2/3/2025 2/14/2025 Mears Group Mears Group - 201 N Fillmore St - E 2nd Ave (N Fillmore St to N Detroit St) 03 Permit Gas Service Tap Gas Service
2/4/2025 2/5/2026 PCL PCL - 201 Fillmore St - N Fillmore St (E 3rd Ave to E 2nd Ave) E 2nd Ave (N Fillmore St to N Detroit St) 05 Permit Sidewalk closure (site closure) Site closure extension
2/10/2025 2/10/2025 PCL PCL - 201 Fillmore St - N Fillmore St (E 3rd Ave to E 2nd Ave) 17 Permit full closure Full closure
2/11/2025 2/14/2025 Dig Boss Colorado Dig Boss SPV LLC dba Dig Boss Colorado - 210 N University Blvd - N University (E 3rd Ave to E 2nd Ave) 01 Permit Fire Line Repair Fire Line Repair