Cherry Creek North (CCN)

The City and County of Denver hosts a monthly construction coordination meeting with key contractors working in the CCN area: N University Blvd to N Steele St and 1st Ave to 3rd Ave.

The purpose of the meeting is to work with contractors to cross-check and coordinate specific street projects within the CCN area and to not have streets inaccessible to motorists/pedestrians at any one time.  Parking may be limited by these projects and lane closures are expected.

A monthly construction schedule of projects and locations is outlined below.  Ongoing construction projects are also listed.  When completion dates are known they will be noted. 

NOTE:  For contractors and others wishing to do work or close streets in the CCN area, you are required to attend the CCN Coordination Meeting prior to starting your work. These meetings are to assist with coordinating all the various CCN Projects. 

Meetings will be held every other month on the third Thursday at 10am.

2401 E 2nd Ave Suite 150 – Basement Boardroom


Work Times - Unless noted, all work times are 8:30am to 3:30pm

Cherry Creek Coordination: 11/16/2022

CCN - Coordination Meeting Notes (11/16/22)(PDF, 5MB)

START END COMPANY LOCATION CLOSURE
11/18/2021 11/21/2022  GH Phipps GH Phipps Construction Company - 200 N Clayton St (E 2nd Ave to E 3rd Ave) Crane for RTU's
1/1/2022 12/31/2022  Cherry Creek North Business Improvement Cherry Creek North Fillmore Plaza IGA Cherry Creek North Fillmore Plaza Annual Permit - IGA
8/11/2022 8/10/2023  GE Johnson GE Johnson Construction Company - 300 N University Blvd - N University Blvd (E 4th Ave to E 3rd Ave) 02 Permit 1st lane Southbound 1st lane closure GE
8/17/2022 11/23/2022  GH Phipps GH Phipps Construction Company - 200 N Clayton St (E 2nd Ave to E 3rd Ave) 02 Alley Intermittent Closures Intermittent closures of the alley
11/1/2022 11/18/2022  Custom Concrete Cutting Inc. Custom Concrete Cutting Inc. - 200 N Clayton St (E 2nd Ave to E 3rd Ave) 06 Permit Alley replacement New Alley install
11/2/2022 2/1/2023  Haselden Construction LLC Haselden Construction LLC - 235 N Fillmore St. - N Fillmore St (E 3rd Ave to E 2nd Ave) 04 Permit Sidewalk Closure Sidewalk closure extension
11/2/2022 2/1/2023  Haselden Construction LLC Haselden Construction LLC - 235 N Fillmore St. - N Fillmore St (E 3rd Ave to E 2nd Ave) 04 Permit Sidewalk Closure Sidewalk Closure
11/4/2022 2/28/2023  GH Phipps GH Phipps Construction Company - 200 N Clayton St (E 2nd Ave to E 3rd Ave) 03 Alley Intermittent Closures Site Closure
11/7/2022 11/23/2022  Xcel Energy - AMRP/CAB Xcel Energy - AMRP CAB - 300 N Fillmore St - E 3rd Ave (N Fillmore to N Milwaukee St) 01 Permit Gas Service Install Gas line
11/14/2022 11/18/2022  AECivil GH Phipps Construction Company - 200 N Clayton St (E 2nd Ave to E 3rd Ave) 07 Permit Water Fire Line Installation Fire Lines
11/15/2022 11/17/2022  Bob Popp Bob Popp Building Services - 2800 E 2nd Ave (N Detroit St to N Fillmore St) 02 Permit Window cleaning
11/15/2022 1/9/2023  Haselden Construction LLC Haselden Construction LLC - 300 N Fillmore St (E 3rd Ave to E 4th Ave) 08 Permit Sidewalk Closure Sidewalk Closure
11/19/2022 11/19/2022  GE Johnson GE Johnson Construction Company - 300 N University Blvd - E 3rd Ave (N Josephine St to N University Blvd) 05 Permit Concrete Pump Concrete Pump