Civic Center Next 100

Rendering of the Civic Center Park Central promenade with the new shade structure that will crete the

Phase One of the Civic Center Next 100 project focuses on three areas of the park: the Greek Theater, Central Promenade and South Plaza. Located at the heart of the city and surrounded by many of our key civic and cultural institutions, Civic Center has served as Denver’s most significant gathering spot for cultural events, festivals, and First Amendment rallies for over 100 years. It is Denver’s first National Historic Landmark and honoring its history is critical as we envision its future. Key features will accommodate traditional uses and also encourage daily active use.

Construction Notice: Nov. 2025

Construction is underway as of November 19, 2025, with completion scheduled for late 2027. Fencing will be around many key areas of the park, however, limited portions will be open and accessible. 

See map for details(PDF, 3MB)-- this map is for illustrative purposes and may change at various points during construction.  


Project Schedule:

  • 2021 - 2022: Concept Design + Public Engagement (complete)
  • Q1 2024 - Q3 2025: Final Design of Phase One
  • Q4 2025: Start of Phase One Construction
  • Q4 2027: Substantial Completion of Phase One (Greek Theater, Central Promenade, South Plaza)

Frequently Asked Questions:

About the Project

What is the Civic Center Next 100 project?

The Civic Center Next 100 project celebrates Denver’s first National Historic Landmark and aims to reinvigorate Civic Center Park for the next 100 years by introducing thoughtful, contemporary updates that will create a premier destination for civic gatherings, community events, cultural performances and daily use. 

Led by Denver Parks & Recreation (DPR) with support from the Civic Center Conservancy and others, the project builds on years of community engagement and fulfills key goals of the community-drafted 2005 Civic Center Master Plan, and the recently published Civic Center Next 100: Civic Center Park + Bannock Street final concept design plan. 


What does the project include?

The first phase of the Civic Center Next 100 is focused on reinvigorating Civic Center Park as a public space that more fully supports both everyday and event use and downtown Denver's flourishing cultural life. 

Key updates include: 

  • A rehabilitated historic Greek Theater with upgraded seating, stage and canopy for contemporary productions and increased use. 
  • Improved accessibility and circulation through pathways that better connect the park. 
  • A new plaza commemorating the Gang of 19 protest and the disability rights movement. 
  • Updated landscape design with new garden rooms, plantings, and plaza areas. 

How does this work differ from the work that was completed during the Civic Center Park closure in 2021-2022?   

Denver Parks & Recreation (DPR) closed Civic Center Park for six months from fall 2021 to spring 2022 due to unsafe conditions—the first such closure in the park's history. During this period, professional restoration work was done, including graffiti removal, mortar replacement, and lighting improvements, all classified as maintenance upgrades. Following the closure, Denver Parks & Recreation was allocated additional budget to increase maintenance standards and ranger presence in the park, which has greatly improved the park conditions and perceptions of safety.   

The current construction project goes beyond maintenance to deliver substantial physical improvements and new amenities, enhancing Civic Center Park's capacity to host contemporary events and performances while improving its everyday usability. 


How does the design honor Civic Center Park’s historic character? 

The design of this revitalization project was carefully crafted with input from historic rehabilitation experts serving on the project's historic advisory committee. Drawing direct inspiration from Edward Bennett's 1918 plan, the new Central Promenade design reestablishes this original pattern of a central walk flanked by two smaller paths, now complemented by loop walks. The project successfully balances historic preservation with contemporary design and modern accessibility requirements, creating accessible routes that follow historic patterns while providing universal access to key features including the Voorhies Memorial and Greek Theater.  

The Greek Theater rehabilitation is particularly noteworthy, featuring a sensitive design that preserves the original structure while introducing an iconic yet subordinate canopy structure and reoriented bowl design. These improvements maintain the theater's historic character while ensuring accessibility to all levels and features, demonstrating how thoughtful design can honor historical integrity while meeting contemporary needs and complying with Denver's Civic Center Guidelines, the Denver Landmark Preservation Guidelines, and the Secretary of the Interior Standards for Rehabilitation. 


Why is this project important for Downtown Denver’s future? 

While Civic Center Park excels at hosting the city’s largest gatherings, it has historically been underutilized for daily activities. These improvements will transform the park into a vibrant everyday destination, drawing more residents and visitors year-round while enhancing downtown’s economic vitality. 

The Civic Center Next 100 project also supports several DPR and City strategic plans, including: 

  • Denver’s Downtown Area Plan (2025)
  • Game Plan for a Healthy City (2019)
  • The Outdoor Downtown plan (2027)
  • Listed as a transformational project in The Parks Legacy Fund Five Year Plan (2025-2029) 

How was the community involved in shaping this project? 

Community engagement has been central to the Civic Center Next 100 project from the beginning. The project fulfills key goals of the 2005 Civic Center Master Plan—a community-drafted vision that laid out principles for balancing the park’s historic preservation with modern functionality and access. 

More recently, a public engagement process in 2021–2022 informed the concept design, followed by a community update in October 2024 to present the final design. Resources from that process are available on DPR’s website: 

Construction and Accessibility

When did construction begin and when will the Park reopen? 

Construction began in Fall 2025. Phase 1 of the Civic Center Next 100 project is expected to be completed with the park fully reopened in late 2027. Construction schedules are subject to change based on weather, supply chains, and field conditions. Denver Parks & Recreation will announce major milestones as they are finalized. 


Is the Park completely closed during construction? 

No. While the central portion of the park including the Central Promenade and the Greek Theater area of the park will be closed during construction, other portions of the park remain open, including: 

  • The Broadway Terrance
  • The area around the Voorhies Memorial 
  • The Great Lawn and Bannock Street in front of Denver’s City & County Building 

Denver Parks & Recreation’s Permitting team is working with the construction contractor and the Civic Center Conservancy to accommodate activations in the park where possible. However, some large events in Civic Center will be affected during the construction period.  


Will the renovations improve accessibility? 

Accessibility is a central goal of this project. For the first time in the Park’s history, the Greek Theater will be fully ADA accessible. New pathways will replace stairs and other barriers throughout the park, ensuring all visitors can move freely and enjoy equal access to key features including the Voorhies Memorial and Greek Theater.

Funding

How is the project funded? 

The Phase 1 design and construction budget totals $50 million, with funding secured through multiple sources and continued active fundraising by Civic Center Conservancy. Sources include: 

  • Denver Parks & Recreation  

  • Downtown Denver Development Authority (DDDA) 

  • Elevate Denver Bond 

  • Mellon Foundation 

  • Private donations facilitated by the Civic Center Conservancy 

Additional elements may be incorporated into the construction project if supplementary funding is secured. 


How do public funding sources and philanthropic contributions work together? 

Private contributions secured through the Civic Center Conservancy and individual donors are designed to work in partnership with the public funding allocated for the Civic Center Next 100 project. While public funding provides the foundation for the project, philanthropic support allows DPR to construct additional features identified in the Next 100 Project that may otherwise have been out of reach, improve the quality of planned amenities, and accelerate improvements so the community can benefit sooner. Together, public funding and private generosity make it possible to restore and reimagine Civic Center Park as the world-class urban public space that Denver deserves.  

Roles and Partnership

What is DPR’s role in the Civic Center Next 100 Project? 

Denver Parks & Recreation (DPR) owns, operates, and maintains Civic Center Park and leads all capital design and construction decisions, procurement, contractor management, and oversight. The City is working with professional design, engineering, and construction teams—including world-renowned lead designer Studio Gang—through established public processes. DPR also manages programming and activations in the park through their permitting process and in partnership with Civic Center Conservancy.   


What is Civic Center Conservancy’s role in this project?

The City and County of Denver is leading the Civic Center Next 100 design and construction project, with the Civic Center Conservancy serving as a critical supporting partner.  

The Conservancy’s role includes the following functions in partnership with DPR: 

  • Financial support: Funded a portion of the design phase and is actively fundraising for construction and future phases
  • Stakeholder engagement: Connects with residents, businesses, civic leaders, and community groups to ensure the project reflects community priorities
  • Communications: Keeps donors, partners, and the public informed in alignment with City-approved messaging
  • Programming: Continues to activate the park during construction and is planning expanded programming for the renovated spaces 
  • Stewardship: Supports DPR’s operational and maintenance investments with volunteerism 

How will the Park be maintained and programmed after construction? 

Denver Parks & Recreation is exploring enhanced maintenance and programming models for Civic Center Park. The addition of new amenities creates opportunities for expanded regular programming, prompting the department to investigate service models that can provide higher levels of maintenance and activity/performance coordination. Throughout this process, Denver Parks & Recreation will maintain its established partnership with the Civic Center Conservancy, which has been the park's long-term programming and stewardship partner.  

What happens to Conservancy programming during construction? 

While some programs have been adapted or paused to accommodate the construction footprint, the Civic Center Conservancy continues to: 

  • Provide free and low-cost public programming throughout construction to keep the park active and thriving
  • Support safe public access where possible in open park areas
  • Maintain donor and community engagement
  • Plan and develop programming for the renovated spaces ahead of reopening 

Construction is a temporary phase that enables a more vibrant, inclusive, and resilient park in the years ahead.

Get Involved & Stay Informed

Donor Engagement and Stewardship:

Donor engagement and stewardship questions can be directed to eb@civiccenterconservancy.org.

Civic Center Conservancy specific events are listed at CivicCenterPark.org


Project Resources:

Several resources are available to follow the Civic Center Next 100 project’s progress: 


Project Background:

Vision Plan Update: October 29, 2024

In partnership with the design team and Civic Center Conservancy, Denver Parks and Recreation hosted a public update on the first implementation phases of the Civic Center Next 100 plan.

Community Engagement

Download the final concept plan(PDF, 13MB)

Workshop #1 | February 11, 2021

The first public meeting covered Civic Center's history and current conditions and invited feedback from the community on how key features of the area should be used, bringing the 2005 park Master Plan to life.

Workshop #2 | June 10, 2021
Workshop #3 | September 23, 2021

At the final public workshop, preferred concept designs were reviewed with the community.


Learn more(PDF, 888KB) | En Español(PDF, 864KB)