The East 16th Avenue Storm Interceptor project area is located in Montclair Basin (Basin 4500-03) of the City and County of Denver Storm Drainage Master Plan. There are existing storm sewers in East 16th Avenue and Batavia Place which are currently undersized to convey the stormwater resulting in frequent and significant flooding of the neighborhood area.  The goal of this project is to work with hydrology developed by the Outfall Systems Plan (OSP) team to size, design, and construct a new storm main line to safely transport the flows from existing systems in Colfax Avenue and East 16th Avenue towards City Park, while picking up the local flows along the way.


Full Closure of 17th Avenue

Closure Information

Beginning Monday, May 17 at 7 a.m., 17th Avenue will fully close for two blocks - from Jackson Street to Colorado Boulevard - for the next four to six months. Detour signs will be posted and message boards have been placed in advance of the closure.


Closure Map 

Closure Information: Closure 001 begins May 17, 2021. 

East 16th Avenue Storm Interceptor project - Road Closure 001 map

Upcoming Closures Map

Closure Information: Closure 002 is expected to begin in September 2021.


Project Details

This project will improve safety and reduce flood risks in the South Park Hill neighborhood by building a new stormwater system which will include installing a larger stormwater pipe to provide additional capacity to carry and drain stormwater in the area.

The existing storm sewers in E. 16th Ave. and Batavia Pl. are currently undersized to adequately convey stormwater levels, resulting in frequent and significant flooding in the South Park Hill neighborhood. The construction includes installing a new stormwater pipe beneath Colorado Boulevard which will connect to the current the stormwater system at City Park Golf Course.
 
In addition to the storm pipe construction, work includes roadway reconfiguration and traffic signal changes at the intersection of E. 17th Ave. and Colorado Blvd., as well as safer crossings for pedestrians and cyclists.
 
Work begins at Jackson Street and E. 17th Avenue, continues east along E. 17th Avenue Parkway, crosses Colorado Blvd and turns south onto Albion Street for approximately 100 feet.

Construction Methods, Impacts and Delays

Weekly Update - April 30, 2021
Status: Message boards with street closure information, and signage showing the suggested detour routes for the upcoming construction will be placed on Monday. You will also see the crew starting to mobilize on site the week of May 17th.
Impacts: Various street closures will be in place on 17th Avenue, Colorado Boulevard, and 17th Avenue Parkway during this project. The first closure will be on 17th Avenue, from the alley west of Jackson Street to Colorado Blvd. This full closure will be in place between 4-6 months. Please refer to the map above.

Reach Out: If you have any questions or concerns just send us an email, call or text the hotline.

Traffic Impacts

Various street closures will be in place on 17th Avenue, Colorado Boulevard and 17th Avenue Parkway when crews are scheduled to work on those stretches. Residences immediately adjacent to the construction site will receive advance notice before work begins on their block. Walk-up access to residents and businesses inside the project area will always be open.

Detour signs and message boards will also be in place throughout the duration of the project to alert commuters about the work and to expect delays. All work is weather dependent and subject to change. Signage will clearly define and direct the detour routes, and we will be sending out weekly impact / detour maps in our email updates — so be sure to sign up for these crucial emails.

The public’s patience and cooperation during construction are greatly appreciated.


Archive Updates

April 2021 - Archive Update

April 30, 2021

Status: Message boards with street closure information, and signage showing the suggested detour routes for the upcoming construction will be placed on Monday. You will also see the crew starting to mobilize on site the week of May 17th.

Impacts: Various street closures will be in place on 17th Avenue, Colorado Boulevard, and 17th Avenue Parkway during this project. The first closure will be on 17th Avenue, from the alley west of Jackson Street to Colorado Blvd. This full closure will be in place between 4-6 months. Please refer to the map above.

Reach Out: If you have any questions or concerns just send us an email, call or text the hotline, or call me directly.