Dec 19, 2019
General Statement of Work
2020 panel replacement throughout the city where concrete failures have occurred. Curb ramps, curbs and gutters will be replaced as necessary.
Estimated Construction Cost
Between $962,289.00 and $1,176,131.00.
Pre-bid on January 7, 2020 at 11:00 a.m.
WEBB Building
201 W. Colfax Avenue
4th Floor Conference Room, 4.I.5
Denver, CO 80202
Questions Deadline
January 14, 2020 at 10:00 a.m. local time
Bid Opening on January 23, 2020 at 11:00 a.m.
WEBB Building
201 W. Colfax Avenue
6th Floor Conference Room 6.G.7
Denver, CO 80202
Plans Available December 19, 2019
QuestCDN Project #6617753
Plan Cost $15.00
M\WBE goal: 20%
Prequalification
1F(2) CONCRETE ROADWAY PAVING at or above the $1,500,000.00 monetary level
Contract Administrator
David Relaford
FOR COMPLETE DESCRIPTION SEE AD IN The Daily Journal ON THE FOLLOWING DATES
Thursday, December 19, 2019
Friday, December 20, 2019
Monday, December 23, 2019