Skip navigation

2017 — Q3 Projects

Routine Deck, Superstructure, and substructure repairs

Construction procurement method: Hard Bid

This project includes the rehabilitation of two concrete culvert crossings. The structures are located at Eastman Avenue over Goldsmith Gulch, and at Monaco/Evans over Goldsmith Gulch. The project include concrete repair, railing rehabilitation, minor drainage and channel improvements, asphalt/roadway work, and compaction grouting for wingwall stabilization.

Construction procurement method: Hard Bid

Westwood Park renovation includes: playground, walks, gardens and lighting.

Construction Procurement Method: Hard Bid

The Rude Park ADA improvement project will bring an existing tier 1 ball field up to current standards. The project will transform the dated and inaccessible bleacher style seating into a sloped walk with retaining walls doubling as seat walls and tiered amphitheater style grass slopes for sitting. The ball field will also be upgraded with improved drainage, new dugouts, backstop, fencing, foul posts, infield mix and equipment, outfield sports turf, and scoreboard. Existing lights and lighting system

Request for Proposals

These contracts will provide on-call SBE construction services to support the Capital Projects Management program, Transportation Division, as well as provide general construction services throughout Public Works, as requested.

The existing South Platte River Drive culvert, open drainage channel, railroad bridge, and Lipan Street box culvert, all within a 900-foot section of Sanderson Gulch are undersized during flood events greater than or equal to a 10-year rain storm event. Currently during rain storm events equal to or greater than a 10-year, floodwaters backup into the drainage channel and overtop in the vicinity of the confluence with the South Platte River.

Construction procurement method: Hard Bid

 

The 2nd phase of the NDCC Sanitary Interceptor improvements would continue a new line east in 49th Avenue to collect the 600-acres and that currently heads north to Lift Station 5.

Construction procurement method: Hard Bid

2017 — Q4 Projects

Building upon the Preliminary Environmental Linkage Study (PEL), this project will improve safety and efficiency, and relieve traffic congestion on Federal Blvd. from 5th Ave. to Howard Pl. These actions will link with existing and planned sections of Federal Blvd. to the north and south, and improve multimodal mobility. Three through lanes in each direction will be constructed, along with a 16-ft. raised median. RAMP funding was procured in late 2013 to complete the project, and in 2014 an EA Checklist will be performed, design will progress, and ROW procurement will commence. Construction of the project will extend into 2018.

Construction procurement method: Hard Bid

Reconstruction of Brighton Blvd. between 44th St. and Race Ct. in order to integrate with the National Western Center Master Plan. Utilizing the 30 percent design which has already been completed, CDOT will construct 44th Street to 47th Avenue. Replacement of Brighton bridge over Race.

Construction: Integrated Contract Work Order

Installation of two trail underpasses under both Colorado Blvd. and Hampden Ave. in order to improve pedestrian and cyclist safety and improve trail connectivity. Two pedestrian box culverts will be installed, with the culvert under Hampden positioned adjacent to the Highline Canal. This project includes Federal STIP funding.

Construction procurement method: Hard Bid

This is the fourth phase of the of the 33rd St. Outfall Project which was originally the 31st and 36th Street Outfall project. This project will extend from Curtis St. to Lafayette St. along 33rd Street.

Construction procurement method: Hard Bid

The general storm program seeks to solve local drainage issues. The locations with this project include 1997 Acoma, 8202 E Lehigh, East Ellsworth, and Hampden Heights.

Construction procurement method: Hard Bid

This project will upgrade an existing 12" sanitary system with a new pipe and alignment. The pipe will run from 13th and Delaware to 11th and Acoma.

Construction procurement method: Hard Bid

2018 — Projected

27th Street Interceptor Phase 1

2016 Annual Sanitary Improvements - Lining
Construction: Hard Bid

Colfax & Lipan Intersection Improvements
Construction Procurement: Hard Bid

High Line Canal Underpass at Parker/Mississippi
RFP

Park Avenue Rehabilitation
Construction Procurement: Hard Bid