Skip navigation

Federal Boulevard Improvements and Reconstruction

 

Denver Public Works is reconstructing a stretch of Federal Boulevard from West 7th Avenue to West Holden Place to enhance safety for people who walk, bike, take transit, and drive the corridor. The enhancements will also improve connectivity between neighborhoods whose residents regularly cross Federal, including Sun Valley residents. 

Construction Update

Week of October 15:  Crews will continue to work on Federal Blvd between W. 7th Ave to W. 10th Ave. and between W. Holden Place to W. 12th Ave. There will be a 24/7 closure for through traffic on W. 9th Avenue east of Federal Boulevard and W. 7th Avenue at Federal Boulevard. Through traffic will be detoured to W 10th Avenue or W 8th Avenue. Starting Monday night, there will also be a single lane closure on northbound Federal Blvd between W. 7th Ave to W. 10th Ave. Business access will be maintained at all times.

Project update (PDF - English/español)

Traffic Impacts & Business Access

Two lanes will remain open in each direction of Federal Boulevard while work is underway. At times, weekend and overnight work may be scheduled, however, there will be prior notification to property and business owners along the corridor. 

There will be lane closures and construction zones on Federal Blvd. and adjacent side streets. Two lanes will remain open in each direction of Federal Boulevard while work is underway. Various minimal closures through the duration of the project will occur to minimize impact to motorists and businesses along the corridor. 

Business and property access will be maintained at all times while work is underway. Work will begin on the south end of the stretch and will be done in phases, moving to West Holden Place.

RTD Impacts

Beginning Tuesday, September 4 there will be a closure for the RTD bus stop along the west side of Federal at Holden Place, RTD stop #13701. The closure is anticipated to be in place until early October. Riders are encouraged to use stop #13702 at Federal Boulevard & 14th Avenue.

Improvements for this project, from W. 7th Ave. to W. Holden Place include:

  • replacing the roadway surface with concrete, which has a longer lifespan
  • three continuous northbound travel lanes 
  • a new raised landscaped median between W. 7th Avenue and W. Holden Place to improve mobility and safety
  • new sidewalks to enhance access to light rail stations and bus stops
  • upgrading the traffic signals at W. 8th and W. 10th Avenues, including installing colored crosswalks to enhance pedestrian visability
  • New trees on the east side of Federal Boulevard
 
Project Status: Construction Beginning

Construction began in July 2018 and will move north from W 5th Avenue to Howard Place. The project is estimated to be complete in early 2020.

Preliminary design began in 2011, following the vision established in the city's Federal Boulevard Corridor Plan in 1995. Final Design & Right-of-Way Procurement was in 2015 to Fall 2017.

Contact Us

Project Information Line
303-482-1071

E-mail
FederalBlvdReconstruction@gmail.com

Questions left on the project line or at the e-mail address will be answered promptly.

Businesses

Contact Denver’s Office of Economic Development for one-on-one assistance managing the potential construction impacts
720-913-1999 | investinDenver@denvergov.org

 

The Federal Highway Administration (FHWA), the Colorado Department of Transportation (CDOT), and City and County of Denver released a Finding of No Significant Impact (FONSI) regarding the Federal Boulevard Improvements Project between West 7th Avenue and West Howard Place. The FONSI is the conclusion of the National Environmental Policy Act process; an Environmental Assessment (EA) was prepared and published for this project. The completion of the FONSI indicates that the project will not cause significant impacts to the human or natural environment and allows the agencies to move forward with implementing the improvements.

Finding of No Significant Impact

Notice of Availability

Notice of Availability (SPANISH Version)

Notice of Availability (KOREAN Version)

The Federal Highway Administration (FHWA), the Colorado Department of Transportation (CDOT), and City and County of Denver announced the availability of the Federal Boulevard Improvements Project between West 7th Avenue and West Howard Place Environmental Assessment (EA). All interested stakeholders were encouraged to review and comment on the EA. The comment period for the EA began on October 15, 2014 and ended November 14, 2014.

Preferred Alternative

FHWA and CDOT have identified a preferred alternative that adds a third northbound lane between West 7th Avenue and West Howard Place, a raised median between West 7th Avenue and West Howard Place, upgrades the existing pedestrian facilities in compliance with the Americans with Disabilities Act throughout the Project Area from West 7th Avenue and West Howard Place, and enhances multimodal connectivity. More information on the Preferred Alternative, its environmental impacts, and mitigation commitments are included in the EA document.

View Public Notice of Availability

These are the EA documents stakeholders commented on:

Environmental Assessment

Environmental Assessment (SPANISH version)

Environment Assessment (KOREAN version)

Archaeological Resources

Historic Resources

Biological Resources

Water Quality

Air Quality

On August 14, 2014, from 5:30pm-7:00pm project planners held an open house at Barnum Recreation Center to discuss the project and provide an update on the NEPA environmental review process as well as the design and timeline for future work.

View the meeting presentation boards

View the power point presentation

Here are the latest design graphics for the Federal Boulevard Project (5th Avenue to Howard Pl). These graphics are for illustration purposes only and should not be considered the final design for the corridor. Some design elements or dimensions may change as final design is completed.

General Cross Section

Access and Parcels

Landscape Plan

Funding to complete this project became available late 2013 through the State of Colorado Responsible Acceleration of Maintenance and Partnerships (RAMP) Program.

Currently, the project is going through an Environmental Assessment (EA) which will update the environmental resource impacts as required by The Colorado Department of Transportation and the Federal Highway Administration.  The EA is expected to be completed in November of 2014.

It is anticipated that a public Open House will be held in the Summer of 2014

Right of Way acquisition is anticipated to begin once the EA is complete in late 2014.

Construction is anticipated to start in late 2016 and extend into 2018.

More information regarding the EA will be posted to this website when it becomes available.

A public meeting was held on October 26, 2011 to discuss the current design. Listed below are meeting presentations and materials as well as a form to submit your comments.


The Federal Highway Administration (FHWA) defines Planning Environmental Linkage (PEL) as a voluntary approach to transportation decision-making that considers environmental, community, and economic goals early in the planning stage and carries them through project development, design, and construction. This can lead to a better decision-making process that minimizes duplication of effort, promotes environmental stewardship, and reduces delays in project implementation.

The Public Works Department began a PEL for Federal Boulevard from 5th Avenue to Howard Place in 2009 to support continued multimodal improvements along Federal Boulevard. These improvements would extend the 3rd northbound lane and median that will be constructed between Alameda and 5th Avenue beginning in the fall of 2010.
 
On April 22, 2009 a Public Meeting was held to discuss and receive feedback on the planned improvements for the roadway.  You may download the presentation posterboards from the public meeting on this site.

The Planning Environmental Linkage (PEL) study which evaluates transportation improvements along Federal Boulevard from 5th Avenue to Howard Place as well as additional reports can be accessed at the links to the right.
 
The City and County of Denver (CCD), in cooperation with the Federal Highway Administration (FHWA) and the Colorado Department of Transportation (CDOT), prepared this PEL Study in accordance with Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) and with FHWA PEL guidance.

The anticipated next step for the 5th Avenue to Howard Place portion of Federal Boulevard is to complete design documents which will provide for an additional 3rd northbound lane and a raised center median within the study area. Currently no funding has been identified for project construction, but the City is completing the design work to be prepared for any funding opportunities that may arise in the near future. 

Federal Boulevard - Howard Place to 20th Avenue  Conceptual Alignment and Interchange Study

 

sample cross section of Federal Boulevard, click to enlarge