Skip navigation

About Park Hill Detention

Park Hill Detention 

 

This new stormwater management system will reduce flooding in the Park Hill area by installing new stormwater pipes along 39th Avenue from Dahlia Street to Grape Street, and near Dahlia Street and Smith Road. The project will also construct a detention area in the northeast corner of Park Hill Golf Course to more effectively hold and slow stormwater that flows through the area. 

 
 

Construction crews are working near Dahlia Street at Smith Road and 39th Avenue, working their way east along 39th Avenue to Grape Street. Initial work involves the removal of asphalt and relocating several existing underground utility pipes.

 

map of project work area 

 
Project Status

Construction began in November 2018 and is planned for completion in 2020. 

 

Construction Updates 

Street Impact Update — As of May 17, 2020

CURRENT CLOSURES

  • Elm Street, south of 39th Avenue
  • Forest Street, south of 39th Avenue
  • 39th Avenue, west of Grape Street
  • 39th Avenue from Eudora to Elm
  • 39th Avenue from Dahlia to Eudora
  • Dahlia Street just north of Smith Road
  • Dahlia Street just south of Smith Road
  • a southbound shoulder closure on Grape Street, near the intersection of 39th Avenue.

We anticipate that all of these stretches of roadway will be open in the June/July time frame.

ROAD WORK: Work on the center median on Smith Road near Dahlia Street will cause a speed reduction.  East and westbound lanes will be maintained - June/July 2020

 

map of closures in Park Hill project area 

Access to businesses and properties will be maintained during construction.

 

Here is the latest landscape design plan for the Park Hill Detention Area and proposed placement of trees around the perimeter, shown as circles. 

Draft Landscape Design Plan (PDF)

Questions about this plan can be directed to ParkHillDetention@PublicInfoTeam.com or 720-990-6400.

latest landscape design plan for the Park Hill Detention Area project

Construction on the Park Hill Detention project continues to progress as scheduled. As of mid-March, the project is 10% complete. Milestones reached include:

  • Boring underneath the train tracks and roadway at Smith Road.
  • Tree and landscape removal at the stormwater detention area.
  • Start of excavation of the stormwater detention area.

Coming in April, crews will be relocating water, storm and sanitary pipes and installing new storm water pipes along 39th Avenue from Dahlia to Elm Street. 

Permanent Detention area location 

  • Installation of construction fencing
  • Removal of landscaping and soil
  • Increased construction traffic
  • Installation of an outlet structure
  • Planting of native grasses

Construction will continue through the end of summer 2019, but is dependent on weather conditions and other factors affecting construction.


Construction Work Hours

Normal working hours along 39th Avenue between Dahlia and Holly Street will be Monday–Friday from 7 a.m. to 9 p.m. and Saturday–Sunday from 8 a.m. to 5 p.m. Unless otherwise noted, street closures are in effect 7 days a week, 24 hours a day. 

Work hours on the stormwater detention area at the Park Hill golf course are limited to Monday–Saturday from 8 a.m. to 5 p.m. 

 

Open House – April 23, 2019

Open House — December 11, 2018

Check back for information on meetings in 2019.

Project Contacts

If you have questions about the project, would like to receive updates, or would like to be notified of upcoming closures, please contact the Public Information Team. We will respond within 24 business hours.

The Project Team will be contacting affected businesses in advance of construction activities.

Project Hotline: 720-990-6400

Email: ParkHillDetention@PublicInfoTeam.com

Sign up to receive traffic impact updates by text: Send “ParkHill” to 313131