This new stormwater management system will reduce flooding in the Park Hill area by installing new stormwater pipes along 39th Avenue from Dahlia Street to Grape Street, and near Dahlia Street and Smith Road. The project will also construct a detention area in the northeast corner of Park Hill Golf Course to more effectively hold and slow stormwater that flows through the area.
Construction crews are working near Dahlia Street at Smith Road and 39th Avenue, working their way east along 39th Avenue to Grape Street. Initial work involves the removal of asphalt and relocating several existing underground utility pipes.
Construction began in November 2018 and is now planned for completion in Fall of 2020.
November 2018 Project Announcement (PDF - English/español)
Traffic Maps
Dahlia Street detours (PDF)
Truck Hauling route (PDF)
Park Hill Storm Phase V Project: October 2017 through December 2018
CURRENT CLOSURES
Access to businesses and properties will be maintained during construction.
Construction on the Park Hill Detention project continues to progress as scheduled. As of mid-March, the project is 10% complete. Milestones reached include:
Coming in April, crews will be relocating water, storm and sanitary pipes and installing new storm water pipes along 39th Avenue from Dahlia to Elm Street.
Construction will continue through the end of summer 2019, but is dependent on weather conditions and other factors affecting construction.
Construction Work Hours
Unless otherwise noted, street closures are 7 days a week, 24-hours a day.
Working hours along 39th Avenue between Dahlia and Holly Street are as follows:
Work hours on the stormwater detention area at the Park Hill Golf Course are as follows:
Access to businesses and properties will be maintained during construction.
Detour routes will be posted to guide motorists and pedestrians around the closures.
The schedule is weather dependent and may change without notice.
Check back for information on meetings in 2019.
If you have questions about the project, would like to receive updates, or would like to be notified of upcoming closures, please contact the Public Information Team. We will respond within 24 business hours.
The Project Team will be contacting affected businesses in advance of construction activities.
Project Hotline: 720-990-6400
Email: ParkHillDetention@PublicInfoTeam.com
Sign up to receive traffic impact updates by text: Send “ParkHill” to 313131