Park Hill Construction Schedule

Schedule subject to change. Updated as of August 2019.

map and timeline for Park Hill Detention project from 2018 through 2019 

Updated August 2019; schedule subject to change due to weather or other events

Beginning November 2018: Pipe and outfall installation, Dahlia Street at Smith Road

Beginning January 2019: Detention area construction in Park Hill Golf Club, northeast corner south of Smith Road

Beginning April 2019: Pipe installation at E 39th Avenue near Dahlia Street

Beginning August 2019: Pipe installation at E 41st Avenue at Dahlia Street 

Beginning September 2019: Pipe installation at E 39th Avenue near Elm Street

Beginning October 2019: Pipe installation at E 39th Avenue near Forest Street

Beginning November 2019: Outlet structure east of E 39th Avenue and Grape Street