2018

July 2018 through June 2019: Pipe installation near Blake/40th Avenue, crossing Walnut Street to Franklin Street

December 2018 through June 2019: Stormwater and pipe installation east of Franklin Street

2019

February 2019 through January 2020: Pipe installation on 39th Avenue from west of Steele Street to Jackson Street

February 2019 through June 2020: Greenway construction on 39th Avenue from Franklin Street to Steele Street

March through November 2019: Bridge construction on York Street

March through November 2019: Pipe installation on 40th Avenue west of Clayton Street

April 2019 through June 2020: Bridge construction on Williams Street

April through December 2019: Pipe installation on Clayton Street north of 40th Avenue

April through August 2019: Pipe installation on Madison and Monroe streets from 39th Avenue to 42nd Avenue

September through November 2019: Pipe installation on 42nd Avenue and Jackson Street