Cherry Creek North (CCN)

The City and County of Denver hosts a monthly construction coordination meeting with key contractors working in the CCN area: N University Blvd to N Steele St and 1st Ave to 3rd Ave.

The purpose of the meeting is to work with contractors to cross-check and coordinate specific street projects within the CCN area and to not have streets inaccessible to motorists/pedestrians at any one time.  Parking may be limited by these projects and lane closures are expected.

A monthly construction schedule of projects and locations is outlined below.  Ongoing construction projects are also listed.  When completion dates are known they will be noted. 

NOTE:  For contractors and others wishing to do work or close streets in the CCN area, you are required to attend the CCN Coordination Meeting prior to starting your work. These meetings are to assist with coordinating all the various CCN Projects. 

Meetings will be held every other month on the third Thursday at 10am.

2401 E 2nd Ave Suite 150 – Basement Boardroom

Work Times

Unless noted, all work times are 8:30am to 3:30pm

Cherry Creek Coordination: 10/15/2020

6/15/2020 7/30/2021 GE Johnson Saint Paul St 2nd Ave to 3rd Ave Parking Lane - Sidewalk Closure 
7/30/2020 10/30/2020 Haselden Construction Clayton St 3rd Ave to 2nd Ave: Clayton St to Columbine St Alley - Closure
7/30/2020 10/30/2020 Haselden Construction Clayton St 3rd Ave to 2nd Ave Sidewalk - Parking Lane Closure
9/7/2020 10/31/2020 True Foods COVID 2nd Ave Detroit St to Fillmore St: Detroit St 1st Ave to 2nd Ave Parking - Lane Closure
9/7/2020 10/31/2020 Hapa Sushi COVID 2nd Ave Milwaukee St to Saint Paul St Sidewalk - Private
9/7/2020 10/31/2020 Bad Daddy's Burgers COVID Milwaukee St 2nd Ave to 3rd Ave Amenity Zone
10/15/2020 10/31/2020 Blue Island Oyster COVID 2nd Ave Clayton St to Columbine St Sidewalk - Parking Lane
9/7/2020 10/31/2020 Syrup COVID 3rd Ave Columbine St to Josephine St Amenity Zone